FRAUD ALERT: PA Turnpike Warns of Ongoing Smishing Scam.

Chat With Us

PA Turnpike Skip to main content
Restore English
Restore English
  •  E-ZPass Login
  •  Pay a Bill
  •  Toll Calculator
  •  Open Road Tolling
  •  Help Center
  •  About Us FAQs
  • E-ZPass
    • About E-ZPass
    • Purchase an E-ZPass
    • Register my E-ZPass
    • Personal Account
    • Commercial Account
    • Toll Calculator
    • All-Electronic Tolling
  • Toll By Plate
    • About Toll By Plate
    • Pay a Bill
    • Toll Calculator
    • PA Toll Pay App
    • All-Electronic Tolling
    • Open Road Tolling
    • Unpaid Tolls/Enforcement
  • Traveling
    • About Traveling
    • Toll Calculator
    • Active Travel Advisories
    • Service Plazas
    • Safety
    • 511PA Travel Information
    • Construction Projects
  • Commercial
    • About Commercial Travel
    • Commercial E-ZPass
    • Permits & Restrictions
    • Service Plazas
    • Toll Calculator
    • Hazardous Materials
  • Business Hub
    • About Working with Us
    • Vendor Portal
    • Vendor Guide
    • Bids & RFPs
    • Vendor Resources
    • Investor Relations
    • Existing Innovation Submission

Galloway Road Bridge

I-95 Interchange Project Design & Construction Details Galloway Road Bridge

Section S1 - S.R. 2023 Bridge

  • Project Overview
  • Design & Construction Details
  • News & Public Involvement
  • Team & Contact Info

Back to Completed Construction

Project Description

As part of the Interchange Project the existing Galloway Road Bridge over the Pennsylvania Turnpike has been replaced to prepare for future additional Turnpike traffic lanes.

The main supports (abutments) of the bridge have been moved further apart. The new bridge is significantly longer than the former bridge and includes two 12-foot wide travel lanes, 8-foot wide shoulders and a pedestrian sidewalk on the east side of the bridge.

The new bridge also has two spans with a new support (pier) in the Turnpike median.

Project Schedule

The construction started in October 2010 with implementation of the detour. Construction was completed in November 2011.

Construction Status

October/November 2011

  • All roadway paving, line striping and bridge fencing completed.
  • Reconstructed bridge re-opened to traffic November 4, 2011, ending 1-year closure.
  • Remaining work includes completing punch-list items, final grading and removing temporary erosion controls.

Image Gallery

Completed new water main attached to bridge (Oct/Nov 2011)

Completed new water main attached to bridge (Oct/Nov 2011)

Contractor staining eastside parapet (Oct/Nov 2011)

Contractor staining eastside parapet (Oct/Nov 2011)

Completed pedestrian sidewalk on new bridge (Oct/Nov 2011)

Completed pedestrian sidewalk on new bridge (Oct/Nov 2011)

Completed new water main attached to bridge (Oct/Nov 2011)
Contractor staining eastside parapet (Oct/Nov 2011)
Completed pedestrian sidewalk on new bridge (Oct/Nov 2011)

Construction Information Archive

September 2011

  • Roadway preparation at the bridge approaches was completed.
  • The contractor began preparation for finish paving on the PA Turnpike mainline median underneath the bridge.
  • Roadway pavement completion anticipated in late-October.
  • The contractor continued forming bridge barriers, expected completion by mid-October.
  • Installation of concrete slope wall began in late-September.
  • Application of coatings and sealants began in late-September.

August 2011

  • The contractor finished placing concrete for the new bridge deck.
  • Roadway preparation continued at the bridge approaches. Completion anticipated in mid-October.
  • The contractor began placing concrete for bridge barriers.
  • Grading was completed for the concrete slope walls.

July 2011

  • Carpenters completed form work for the new bridge deck and barriers.
  • The contractor began to place concrete for the new bridge deck. Deck placements are ongoing and will continue with expected completion in mid-August.
  • Roadway grading and utility installation work continued at the bridge approaches.
  • The contractor completed placement of topsoil and seeding on the north side of the bridge.

June 2011

  • Contractor installed new bridge beams in late-May.
  • Contractor is currently installing new utilities.
  • Contractor will begin constructing the new bridge look.

April 2011

  • The contractor is currently constructing the new bridge supports (abutments and pier).
  • The new approach embankments (fill) are currently under construction.
  • The contractor is currently preparing to install the new bridge beams in early summer.

More Project Resources

Project Overview

Learn about I-95 Interchange Project.

Learn More

News & Public Involvement

Learn how we stay connected with the public about this project.

Stay Updated

Team & Contact Information

Learn about the team that we will work with to complete the work on this project.

Contact the Team

  • About Us
    • Our Mission
    • Our Board of Commissioners
    • Commission Meeting Information
    • Our Executive Leadership
    • Design & Construction
    • PA Turnpike History
    • Investor Relations
    • Resource Library
    • Policies & Standards
    • Security & Fraud
    • About Us FAQs
  • News
    • Traffic Reports
    • The Road Ahead: Turnpike Newsletter
    • Stories from the Turnpike
    • Media Center
    • PA Turnpike Blogs
    • Right to Know Request
    • Law Enforcement Requests
    • Vehicle Registration Suspension Appeals
  • Responsibility Matters
    • Sustainability
    • Clean Water
    • Accountability
    • PA Mobility Partnership Reports
    • National Center for Missing and Exploited Children
    • Human Trafficking Awareness
  • Contract/PO Search
  • Careers
  • Contact Us
  • Site Map
  • Employee Login
  • Facebook
  • Twitter
  • Instagram
  • Linkedin
  • YouTube

©2025 The Pennsylvania Turnpike Commission