FRAUD ALERT: PA Turnpike Warns of Ongoing Smishing Scam.

Chat With Us

PA Turnpike Skip to main content
Restore English
Restore English
  •  E-ZPass Login
  •  Pay a Bill
  •  Toll Calculator
  •  Open Road Tolling
  •  Help Center
  •  About Us FAQs
  • E-ZPass
    • About E-ZPass
    • Purchase an E-ZPass
    • Register my E-ZPass
    • Personal Account
    • Commercial Account
    • Toll Calculator
    • All-Electronic Tolling
  • Toll By Plate
    • About Toll By Plate
    • Pay a Bill
    • Toll Calculator
    • PA Toll Pay App
    • All-Electronic Tolling
    • Open Road Tolling
    • Unpaid Tolls/Enforcement
  • Traveling
    • About Traveling
    • Toll Calculator
    • Active Travel Advisories
    • Service Plazas
    • Safety
    • 511PA Travel Information
    • Construction Projects
  • Commercial
    • About Commercial Travel
    • Commercial E-ZPass
    • Permits & Restrictions
    • Service Plazas
    • Toll Calculator
    • Hazardous Materials
  • Business Hub
    • About Working with Us
    • Vendor Portal
    • Vendor Guide
    • Bids & RFPs
    • Vendor Resources
    • Investor Relations
    • Existing Innovation Submission

Bristol-Oxford Valley Road Bridge

I-95 Interchange Project Design & Construction Details Bristol-Oxford Valley Road Bridge

Section S1 - S.R. 2029 Bridge

  • Project Overview
  • Design & Construction Details
  • News & Public Involvement
  • Team & Contact Info

Back to Completed Construction

Project Description

As part of the Interchange Project the existing bridge over the Pennsylvania Turnpike has been replaced to prepare for future additional Turnpike traffic lanes and ramps.

The main supports (abutments) of the bridge have been moved further apart. The new bridge is significantly longer than the former bridge and includes two 12-foot wide travel lanes and 8-foot wide shoulders.

The new bridge also has two spans with a new support (pier) in the Turnpike median.

Project Schedule

The construction started in October 2010 with implementation of the detour. Construction was completed in November 2011.

Construction Status

October/November 2011

  • All roadway paving, line striping and bridge fencing completed.
  • Reconstructed bridge re-opened to traffic November 4, 2011, ending 1-year closure.
  • Remaining work includes completing punch-list items, final grading and removing temporary erosion controls.

Image Gallery

Installing new guide rail on south side Sep 2011

Installing new guide rail on south side Sep 2011

Completed new median pier (Oct/Nov 2011)

Completed new median pier (Oct/Nov 2011)

Completed north side roadway (Oct/Nov 2011)

Completed north side roadway (Oct/Nov 2011)

Installing new guide rail on south side Sep 2011
Completed new median pier (Oct/Nov 2011)
Completed north side roadway (Oct/Nov 2011)

Construction Information Archive

September 2011

  • Bridge barrier work was completed.
  • The contractor began preparation for finish paving on the PA Turnpike mainline median underneath the bridge.
  • The contractor began roadway driving surface preparation in late-September.
  • Roadway pavement completion anticipated in late-October.
  • Work at the bridge approaches continued, expected completion in late-October.
  • Application of coatings and sealants began in late-September.

August 2011

  • The contractor completed placing concrete for the new bridge deck.
  • Work at the bridge approaches will continue through October.
  • Barrier work began and is anticipated for completion by late-September.
  • PECO completed gas main installation on the bridge and roadway approaches.

July 2011

  • PECO continued gas main installation on the bridge and roadway approaches.
  • Carpenters continued forming end diaphragms for the bridge superstructure.
  • Grading for sub-base and new pavement began and will continue at the bridge approaches.
  • Placement of bridge deck concrete is anticipated to start in mid-August.

June 2011

  • Contractor installed new bridge beams in mid-June
  • Work to install the new bridge deck and utilities will start in late-June.

April 2011:

  • The contractor is constructing the new bridge supports (abutments and pier).
  • The new approach embankments (fill) are currently under construction.
  • The contractor is currently preparing to install the new bridge beams in early summer

More Project Resources

Project Overview

Learn about I-95 Interchange Project.

Learn More

News & Public Involvement

Learn how we stay connected with the public about this project.

Stay Updated

Team & Contact Information

Learn about the team that we will work with to complete the work on this project.

Contact the Team

  • About Us
    • Our Mission
    • Our Board of Commissioners
    • Commission Meeting Information
    • Our Executive Leadership
    • Design & Construction
    • PA Turnpike History
    • Investor Relations
    • Resource Library
    • Policies & Standards
    • Security & Fraud
    • About Us FAQs
  • News
    • Traffic Reports
    • The Road Ahead: Turnpike Newsletter
    • Stories from the Turnpike
    • Media Center
    • PA Turnpike Blogs
    • Right to Know Request
    • Law Enforcement Requests
    • Vehicle Registration Suspension Appeals
  • Responsibility Matters
    • Sustainability
    • Clean Water
    • Accountability
    • PA Mobility Partnership Reports
    • National Center for Missing and Exploited Children
    • Human Trafficking Awareness
  • Contract/PO Search
  • Careers
  • Contact Us
  • Site Map
  • Employee Login
  • Facebook
  • Twitter
  • Instagram
  • Linkedin
  • YouTube

©2025 The Pennsylvania Turnpike Commission