FRAUD ALERT: PA Turnpike Warns of Ongoing Smishing Scam.

Chat With Us

PA Turnpike Skip to main content
Restore English
Restore English
  •  E-ZPass Login
  •  Pay a Bill
  •  Toll Calculator
  •  Open Road Tolling
  •  Help Center
  •  About Us FAQs
  • E-ZPass
    • About E-ZPass
    • Purchase an E-ZPass
    • Register my E-ZPass
    • Personal Account
    • Commercial Account
    • Toll Calculator
    • All-Electronic Tolling
  • Toll By Plate
    • About Toll By Plate
    • Pay a Bill
    • Toll Calculator
    • PA Toll Pay App
    • All-Electronic Tolling
    • Open Road Tolling
    • Unpaid Tolls/Enforcement
  • Traveling
    • About Traveling
    • Toll Calculator
    • Active Travel Advisories
    • Service Plazas
    • Safety
    • 511PA Travel Information
    • Construction Projects
  • Commercial
    • About Commercial Travel
    • Commercial E-ZPass
    • Permits & Restrictions
    • Service Plazas
    • Toll Calculator
    • Hazardous Materials
  • Business Hub
    • About Working with Us
    • Vendor Portal
    • Vendor Guide
    • Bids & RFPs
    • Vendor Resources
    • Investor Relations
    • Existing Innovation Submission

Design & Construction Details

Beaver River Bridge Replacement Project Design & Construction Details
  • Project Overview
  • Design & Construction Details
  • News & Public Involvement
  • Team & Contact Info

Construction Activities

 

Fall 2025 Construction:

The project is currently in stage 4 construction.  The mainline PA Turnpike lanes have been shifted southward to allow for earthwork, grading, and asphalt paving for the realignment of the roadway to meet the new river crossing structures.  All 4 piers and Pier Tables for the westbound Beaver River Bridge Crossing have been completed.  15-Foot-long segmental concrete placements have been completed from the westbound Piers 1 & 4 headings.  Form Travelers are being transferred to westbound Piers 2 & 3 for segmental construction at those headings which will be performed during the fall and winter into 2026. Two piers (1 & 4) have been completed for the eastbound Beaver River Bridge Crossing and pier table construction is nearly complete at these piers.  Pier construction is in progress for piers 2 & 3 with completion scheduled for early 2026.  Most of the project excavation has been completed for the new roadway realignment with limited excavation remaining for the new configuration of the Beaver Valley Interchange which will continue into 2026.  Bridge deck construction for WB-209 (I-76 over SR-0018) has been completed, and the remaining superstructure work will be completed this fall.  Mainline roadway and interchange storm drainage activities continue as well as Erosion and Sedimentation control.

Big Beaver Boulevard (SR-0018) reconstruction continues with traffic shifted to the newly reconstructed northbound lanes.  Reconstruction of the existing southbound lanes will continue through the fall of 2025.  New sanitary sewer line construction and upgraded storm drainage have been completed.  Traffic flow on and off I-76 eastbound and westbound are in temporary ramp configurations so please use caution and follow posted signage when entering and exiting the Turnpike.  Please use caution through the construction zone for intermittent flagging activities and construction vehicles as they enter/exit the work areas.

River Road (SR-1001) is currently in a single lane configuration through the construction zone for form traveler and pier table construction.  Traffic controlled by temporary traffic signal.  Thank you for your patience.

Thompson Run Road was closed to traffic on July 23, 2023, for regrading and realignment and will reopen when construction activities permit.


September 2025

Ramp-J-Concrete-Pavement-2025-09-22

Aerial-Photo-Looking-Westward-2025-09-02

WB-Pier-Table-Progress-Looking-West-2025-09-22

Aerial-Photo-Looking-Eastward-2025-09-01

Pier-4-WB-Internal-Core-Formwork-2025-09-04

WB209-WB-Deck-Placement-2025-09-10

Aerial-Photo-Interchange-Construction-2025-09-02

WB209-WB-Deck-Dry-Run-2025-09-09

Pier-4-WB-Interior-Segment-Core-2025-09-04

EB-Pier 3-Lift-Concrete-Placement-2025-09-30

Form-Traveler-Removal-2025-09-22

Pier-4-WB-Internal-Core-Formwork-2025-09-04

WB209a-Set-Abut-1-Expansion-Dam-2025-09-11

Ramp-J-Concrete-Pavement-2025-09-22
Aerial-Photo-Looking-Westward-2025-09-02
WB-Pier-Table-Progress-Looking-West-2025-09-22
Aerial-Photo-Looking-Eastward-2025-09-01
Pier-4-WB-Internal-Core-Formwork-2025-09-04
WB209-WB-Deck-Placement-2025-09-10
Aerial-Photo-Interchange-Construction-2025-09-02
WB209-WB-Deck-Dry-Run-2025-09-09
Pier-4-WB-Interior-Segment-Core-2025-09-04
EB-Pier 3-Lift-Concrete-Placement-2025-09-30
Form-Traveler-Removal-2025-09-22
Pier-4-WB-Internal-Core-Formwork-2025-09-04
WB209a-Set-Abut-1-Expansion-Dam-2025-09-11

August 2025

Ramp-J-Asphalt-Base-and-Roadway-Formwork-2025-08-20

Pier-2-Pier-Table-2025-08-02

Pier-4-Segment-Progress-2025-08-18

Segment-Rebar-and-PT-Ducts-2025-08-16

Project-Overview-Looking-West2025-08-22

Project-Overview-Looking-East-2025-08-10

Pier-1-Segment-Progress-2025-08-06

Pier-1-Form-Traveler-2025-08-20

Ramp-J-Asphalt-Base-and-Roadway-Formwork-2025-08-20
Pier-2-Pier-Table-2025-08-02
Pier-4-Segment-Progress-2025-08-18
Segment-Rebar-and-PT-Ducts-2025-08-16
Project-Overview-Looking-West2025-08-22
Project-Overview-Looking-East-2025-08-10
Pier-1-Segment-Progress-2025-08-06
Pier-1-Form-Traveler-2025-08-20

July 2025

WB209-EB-Deck-placement-2025-07-11

West-Basing-Grading at-Interchange-2025-07-25

Pier-Construction-Looking-West-2025-07-21

WB-Pier-Table-Construction-Looking-East-2025-07-29

Pier-1-Segment-Progress-2025-07-28

Pier-4-Segment-Progress-2025-07-01

Post-Tesioning-of-Segment-Tendons-2025-07-29

Inside-of-Concrete-Segments-2025-07-29

Pier-2EB-Lift-2-Formwork-2025-07-29

Concrete-Placement-for-Pier-4EB-Pier-Table-Walls-2025-07-29

Grading-Subgrade-at-Ramp-J-2025-07-28

WB209-EB-Deck-placement-2025-07-11
West-Basing-Grading at-Interchange-2025-07-25
Pier-Construction-Looking-West-2025-07-21
WB-Pier-Table-Construction-Looking-East-2025-07-29
Pier-1-Segment-Progress-2025-07-28
Pier-4-Segment-Progress-2025-07-01
Post-Tesioning-of-Segment-Tendons-2025-07-29
Inside-of-Concrete-Segments-2025-07-29
Pier-2EB-Lift-2-Formwork-2025-07-29
Concrete-Placement-for-Pier-4EB-Pier-Table-Walls-2025-07-29
Grading-Subgrade-at-Ramp-J-2025-07-28

June 2025

Mainline-Roadway-Widening-Approacing-Abutment-2-2025-06-18

Pier-4-Segment-Construction-2025-06-10

Pier-1EB-Pier-Table-Construction-2025-06-04

River-Tressel-Crane-Work-2025-06-10

WB-Pier-1-As-Cast-Survey-2025-06-02

Mainline-Roadway-Widening-Looking-East-2025-06-18

Pier-3WB-Pier-Table-Construction-2025-06-26

WB-209A-Bridge-Deck-Placement-2025-06-01

Piers-1-and-2-Looking-West-2025-06-10

Mainline-Roadway-Widening-Looking-West-2025-06-18

Mainline-Roadway-Widening-Approacing-Abutment-2-2025-06-18
Pier-4-Segment-Construction-2025-06-10
Pier-1EB-Pier-Table-Construction-2025-06-04
River-Tressel-Crane-Work-2025-06-10
WB-Pier-1-As-Cast-Survey-2025-06-02
Mainline-Roadway-Widening-Looking-East-2025-06-18
Pier-3WB-Pier-Table-Construction-2025-06-26
WB-209A-Bridge-Deck-Placement-2025-06-01
Piers-1-and-2-Looking-West-2025-06-10
Mainline-Roadway-Widening-Looking-West-2025-06-18

May 2025

Tremie-Seal-Pier-3-EB-2025-05-13

WB-211-Aerial-Photo-Looning-South-2025-05-01

WB-211-Aerial-Photo-Looking-West-2025-05-02

Pier-4-Looking-Sta-Ahead-from-Pier-3-2025-05-13

Pier-4-WB-Segment-Placement-2025-05-14

WB-Pier-4-Survey-2025-05-07

WB-Pier-1-Internal-Forms-2025-05-07

WB-Pier-4-2025-05-22

WB-211-Progress-Looking-West-2025-05-19

Pier-1-WB-Survey-2025-05-30

Tremie-Seal-Pier-3-EB-2025-05-13
WB-211-Aerial-Photo-Looning-South-2025-05-01
WB-211-Aerial-Photo-Looking-West-2025-05-02
Pier-4-Looking-Sta-Ahead-from-Pier-3-2025-05-13
Pier-4-WB-Segment-Placement-2025-05-14
WB-Pier-4-Survey-2025-05-07
WB-Pier-1-Internal-Forms-2025-05-07
WB-Pier-4-2025-05-22
WB-211-Progress-Looking-West-2025-05-19
Pier-1-WB-Survey-2025-05-30

April 2025

Pier4-EB-WB-Looking-West-2025-04-09

WB-Pier-1-1D-Segment-2025-04-02

WB-Pier-3-2025-04-09

Basin-Slope-Stabilization-2025-04-09

U-Company-installing-shrubs-along-Channel-13-2025-04-07

WB-Pier-1-2U-Rebar-and-PT-Ducts-2025-04-16

Segment-P4-2U-Concrete-Placement-2025-04-16

Pier-4-1D-Bottom-Rebar-2025-04-16

Concrete-Finishing-Segment-P4-1D-2025-04-12

Project-Overview-2025-04-01

Pier-Construction-Looking-East-2025-04-16

Pier4-EB-WB-Looking-West-2025-04-09
WB-Pier-1-1D-Segment-2025-04-02
WB-Pier-3-2025-04-09
Basin-Slope-Stabilization-2025-04-09
U-Company-installing-shrubs-along-Channel-13-2025-04-07
WB-Pier-1-2U-Rebar-and-PT-Ducts-2025-04-16
Segment-P4-2U-Concrete-Placement-2025-04-16
Pier-4-1D-Bottom-Rebar-2025-04-16
Concrete-Finishing-Segment-P4-1D-2025-04-12
Project-Overview-2025-04-01
Pier-Construction-Looking-East-2025-04-16

March 2025

Wb-Pier-1-1D-Segment-Formwork-2025-03-28

WB-and-EB-Pier-1-2025-03-28

WB-Pier-4-2025-03-27

Roadway-Widening-and-Grading-Looking-West-2025-03-04

Project-Overview-Looking-West-2025-03-01

WB-Pier-1-Second-PIcture-2025-03-25

Project-Overview-2025-03-07

WB-Pier-3-2025-03-05

WB-Pier-4-1U-Tranverse-Tendon-Epoxy-Pourbacks-2025-03-04

Wb-Pier-1-1D-Segment-Formwork-2025-03-28
WB-and-EB-Pier-1-2025-03-28
WB-Pier-4-2025-03-27
Roadway-Widening-and-Grading-Looking-West-2025-03-04
Project-Overview-Looking-West-2025-03-01
WB-Pier-1-Second-PIcture-2025-03-25
Project-Overview-2025-03-07
WB-Pier-3-2025-03-05
WB-Pier-4-1U-Tranverse-Tendon-Epoxy-Pourbacks-2025-03-04

February 2025

Piers-3-4-WB-and-Pier-4-EB-2025-02-27

Pier-3-WB-2025-02-27

Pier-4-WB-Segment-4U1-Traveler-Formwork-2025-02-08

WB Piers-1-3-2025-02-17

Project-Overview-2-2025-02-12

WB-Pier-1-1U-Pre-Pour-2025-02-26

Pier-4WB-Segment-1U-Concrete-Pumping-2025-02-27

Pier-4-WB-2025-02-07

Top-of-Pier-4-WB-Looking-West-2025-02-27

Pier-4WB-Segment-1U-Concrete-Placement-2025-02-27

Piers-3-4-WB-and-Pier-4-EB-2025-02-27
Pier-3-WB-2025-02-27
Pier-4-WB-Segment-4U1-Traveler-Formwork-2025-02-08
WB Piers-1-3-2025-02-17
Project-Overview-2-2025-02-12
WB-Pier-1-1U-Pre-Pour-2025-02-26
Pier-4WB-Segment-1U-Concrete-Pumping-2025-02-27
Pier-4-WB-2025-02-07
Top-of-Pier-4-WB-Looking-West-2025-02-27
Pier-4WB-Segment-1U-Concrete-Placement-2025-02-27

January 2025

Pier-4-Form-Traveler-Installation-2025-01-08

Pier-4-WB-Form-Traveler-2025-01-08

Project-Progress-Looking-West-2025-01-08

WB-Pier-4-2025-01-24

Mainline-Roadway-Grading-Looking-East-2025-01-08

Pier-3-EB-Cofferdam-2025-01-08

Pier-Construction-Looking-Westward-2025-01-08

WB-Pier-3-Pier-Table-Falsework-2025-01-22

Pier-1-WB-and-EB-2025-01-09

Bridge-Construction-Overview-2025-01-08

Pier-4-Form-Traveler-Installation-2025-01-08
Pier-4-WB-Form-Traveler-2025-01-08
Project-Progress-Looking-West-2025-01-08
WB-Pier-4-2025-01-24
Mainline-Roadway-Grading-Looking-East-2025-01-08
Pier-3-EB-Cofferdam-2025-01-08
Pier-Construction-Looking-Westward-2025-01-08
WB-Pier-3-Pier-Table-Falsework-2025-01-22
Pier-1-WB-and-EB-2025-01-09
Bridge-Construction-Overview-2025-01-08

December 2024

EB-Pier-3-Coffer-Dam-Test-Drilling-2024-12-10

WB-Pier-1-Form-Traveler-Construction-2024-12-30

WB-Pier 4-Form-Traveler-2024-12-20

WB-Pier-4-and-Abutment-2-2024-12-03

WB-Pier-3-Rebar-2024-12-11

WB-Piers-1-and-2-and-EB-Pier-1-2024-12-06

Project-Overview-Looking-West-2024-12-01

Placing-Stockpiled-R-Rock-2024-12-05

WB-and-EB-Pier-4-2024-12-05

WB-and-E- Pier-1-2024-12-03

EB-Pier-3-Coffer-Dam-Test-Drilling-2024-12-10
WB-Pier-1-Form-Traveler-Construction-2024-12-30
WB-Pier 4-Form-Traveler-2024-12-20
WB-Pier-4-and-Abutment-2-2024-12-03
WB-Pier-3-Rebar-2024-12-11
WB-Piers-1-and-2-and-EB-Pier-1-2024-12-06
Project-Overview-Looking-West-2024-12-01
Placing-Stockpiled-R-Rock-2024-12-05
WB-and-EB-Pier-4-2024-12-05
WB-and-E- Pier-1-2024-12-03

November 2024

WB-Pier-3-2024-11-22

WB-Pier-1-Dancefloor-Removal-Picture-1-2024-11-19

WB-Pier-4-Diaphragm-Tendon-Stressing-2024-11-19

WB-Pier-4-2024-11-22

WB-209-2024-11-20

Site-Overview-2024-11-20

East-Stormwater-Basin-Construction-2024-11-04

WB-Pier-2-Concrete-Placement-2024-11-05

WB-Pier-2-Formwork-2024-11-01

Pier-1-WB-and-EB-2024-11-26

WB-Pier-3-2024-11-22
WB-Pier-1-Dancefloor-Removal-Picture-1-2024-11-19
WB-Pier-4-Diaphragm-Tendon-Stressing-2024-11-19
WB-Pier-4-2024-11-22
WB-209-2024-11-20
Site-Overview-2024-11-20
East-Stormwater-Basin-Construction-2024-11-04
WB-Pier-2-Concrete-Placement-2024-11-05
WB-Pier-2-Formwork-2024-11-01
Pier-1-WB-and-EB-2024-11-26

October 2024

WB-211-Construction-Looking-East-2024-10-15

WB-Pier-4-As-Cast-Survey-2024-10-17

WB-Pier-4-Top-Slab-Formwork-2024-10-09

Pier-4WB-Concrete-Placement-for-Pier-Table-Top-Slab-2024-10-15

Pier-4WB-Concrete-Placement-Looking-West-2024-10-15

Site-Overview-Looking-West-2024-10-31

West-Access-Road-Looking-East-2024-10-08

WB-Pier-2-EB-and-WB-Pier-1-2024-10-11

WB-Pier-4-Pier-Table-Pourbacks-2024-10-29

WB-209-Diaphragm-Concrete-Placement-2024-10-02

Subgrade-Preparation-for-Westbound-Roadway-Widening-2024-10-15

WB-211-Construction-Looking-East-2024-10-15
WB-Pier-4-As-Cast-Survey-2024-10-17
WB-Pier-4-Top-Slab-Formwork-2024-10-09
Pier-4WB-Concrete-Placement-for-Pier-Table-Top-Slab-2024-10-15
Pier-4WB-Concrete-Placement-Looking-West-2024-10-15
Site-Overview-Looking-West-2024-10-31
West-Access-Road-Looking-East-2024-10-08
WB-Pier-2-EB-and-WB-Pier-1-2024-10-11
WB-Pier-4-Pier-Table-Pourbacks-2024-10-29
WB-209-Diaphragm-Concrete-Placement-2024-10-02
Subgrade-Preparation-for-Westbound-Roadway-Widening-2024-10-15

September 2024

Aerial-Photo-nterchange-Looking-North-2024-09-05

Aerial-Photo-WB-211-Overview-Looking-SouthWest2-2024-09-05

Aerial-Photo-Pier-1-Closeup-Looking-East-2024-09-05

WB-Pier3-Lift4-Curing-2024-09-30

Aerial-Photo-NFS-Above-ML-Looking-East-2024-09-05

WB-211-Construction-Looking-West-2024-09-05

WB-209-Superstructure-Construction-over-SR-0018-2024-09-27

WB-211-Construction-2024-09-27

Aerial-Photo-Above-Abut-1-WB-211-Looking-East-2-2024-09-05

Pier-1-Pier-Table-Rebar-Duct-Installation-2024-09-27

Pier-1-WB-Pier-Table-Top-Deck-Pour-2024-09-29

Aerial-Photo-nterchange-Looking-North-2024-09-05
Aerial-Photo-WB-211-Overview-Looking-SouthWest2-2024-09-05
Aerial-Photo-Pier-1-Closeup-Looking-East-2024-09-05
WB-Pier3-Lift4-Curing-2024-09-30
Aerial-Photo-NFS-Above-ML-Looking-East-2024-09-05
WB-211-Construction-Looking-West-2024-09-05
WB-209-Superstructure-Construction-over-SR-0018-2024-09-27
WB-211-Construction-2024-09-27
Aerial-Photo-Above-Abut-1-WB-211-Looking-East-2-2024-09-05
Pier-1-Pier-Table-Rebar-Duct-Installation-2024-09-27
Pier-1-WB-Pier-Table-Top-Deck-Pour-2024-09-29

August 2024

Pier-4WB-Pier-Table-Formwork-2024-08-23

Project-Progress-Looking-Westward-2024-08-26

Caisson-Installation-for-Pier-2EB-2024-08-23

Pier-1WB-Pier-Table-Formwork-2024-08-13

Concrete-Placement-for-Ramp-JK-at-SR-0018-2024-08-26

Concrete-Placement-for-Pier-1WB-Pier-Table-Walls-2024-08-13

Excavation-and-Grading-for-Mainline-Turnpike-Widening-2024-08-26

Mainline-Grading-and-Widening-Looking-West-2024-08-26

Pier-4WB-Pier-Table-Formwork-2024-08-23
Project-Progress-Looking-Westward-2024-08-26
Caisson-Installation-for-Pier-2EB-2024-08-23
Pier-1WB-Pier-Table-Formwork-2024-08-13
Concrete-Placement-for-Ramp-JK-at-SR-0018-2024-08-26
Concrete-Placement-for-Pier-1WB-Pier-Table-Walls-2024-08-13
Excavation-and-Grading-for-Mainline-Turnpike-Widening-2024-08-26
Mainline-Grading-and-Widening-Looking-West-2024-08-26

July 2024

Pier-4-EB-Pier-Shafts-2024-07-31

Existing-Beaver-River-Bridge-from-Pier-4WB-2024-07-31

Concrete-Placement-for-Pier-2WB-2nd-Lift-2024-07-11

View-From-Pier-4WB-Looking-West-2024-07-31

New-Thompson-Run-Road-Grading-2024-07-17

Grading-on-East-End-of-Progect-2024-07-31

Pier-4WB-Pier-Table-Diaphragm-Rebar-2024-07-31

Pier-4-EB-Pier-Shafts-2024-07-31
Existing-Beaver-River-Bridge-from-Pier-4WB-2024-07-31
Concrete-Placement-for-Pier-2WB-2nd-Lift-2024-07-11
View-From-Pier-4WB-Looking-West-2024-07-31
New-Thompson-Run-Road-Grading-2024-07-17
Grading-on-East-End-of-Progect-2024-07-31
Pier-4WB-Pier-Table-Diaphragm-Rebar-2024-07-31

June 2024

Concrete-Beam-Staging-along-SR-0018-.2024-06-20

Setting-Concrete-Beams-over-SR-0018-2024-06-24

Pier-1-WB-Pier-Table-Base-Rebar-Installation-2024-06-04

Pier-3-WB-Top-of-Tremie-Seal-2024-06-04

Concrete-Beam-Setting-over-SR-0018-2024-06-20

WB-211-Pier-1-2-Construction-Looking-West-2024-06-27

Pier-1-WB-Pier-Table-Base-Pour-2024-06-19

WB-211-Pier-4-WB-Pier-Table-Formwork-2024-06-27

Pier-1-WB-Pier-Table-Base-Pour2-2024-06-19

Concrete-Beam-Staging-along-SR-0018-.2024-06-20
Setting-Concrete-Beams-over-SR-0018-2024-06-24
Pier-1-WB-Pier-Table-Base-Rebar-Installation-2024-06-04
Pier-3-WB-Top-of-Tremie-Seal-2024-06-04
Concrete-Beam-Setting-over-SR-0018-2024-06-20
WB-211-Pier-1-2-Construction-Looking-West-2024-06-27
Pier-1-WB-Pier-Table-Base-Pour-2024-06-19
WB-211-Pier-4-WB-Pier-Table-Formwork-2024-06-27
Pier-1-WB-Pier-Table-Base-Pour2-2024-06-19

May 2024

Placing-Concrete-for-Pier-3-WB-Tremie-Seal-2024-05-14

Inside-of-Pier-3-WB-Cofferdam-2024-05-18

Concrete-Placement-for-Pier-4-EB-2024-05-08

Lifting-of-Formwork-for-Pier-1-WB-Pier-Table-2024-05-08

Project-Progress-Looking-West-2024-05-03

Placement-of-Formwork-for-Pier-4-WB-Pier-Table-2024-05-23

Pier-3-WB-Air-Lifting-2024-05-06

Excavation-and-Grading-for-Future-Thompson-Run-Road-2024-05-22

Rebar-Installation-for-Pier 3-WB-Footing-2024-05-14

Placing-Concrete-for-Pier-3-WB-Tremie-Seal-2024-05-14
Inside-of-Pier-3-WB-Cofferdam-2024-05-18
Concrete-Placement-for-Pier-4-EB-2024-05-08
Lifting-of-Formwork-for-Pier-1-WB-Pier-Table-2024-05-08
Project-Progress-Looking-West-2024-05-03
Placement-of-Formwork-for-Pier-4-WB-Pier-Table-2024-05-23
Pier-3-WB-Air-Lifting-2024-05-06
Excavation-and-Grading-for-Future-Thompson-Run-Road-2024-05-22
Rebar-Installation-for-Pier 3-WB-Footing-2024-05-14

April 2024

Aerial-Photo-Intersection-SR0018-Looking West-2024-04-24

Beaver-River-Work-Zone-Flooding-2024-04-03

Pier-4-Construction-Looking-West-2024-04-16

Aerial-Photo-Across-River-TRR-Looking-East-2024-04-24

Aerial-Photo-East-Side-Overview-Looking-NorthEast-2024-04-24

Inside-Pier-2-Cofferdam-Top-of-Tremie-Seal-2024-04-01

Pier-4-Construction-2024-04-03

Class-I-Excavation-East-Side-to-River-2024-04-17

Thermoplastic-Pipe-Installation-for-Thompson-Run-Rd-2024-04-05

Aerial-Photo-Intersection-SR0018-Looking West-2024-04-24
Beaver-River-Work-Zone-Flooding-2024-04-03
Pier-4-Construction-Looking-West-2024-04-16
Aerial-Photo-Across-River-TRR-Looking-East-2024-04-24
Aerial-Photo-East-Side-Overview-Looking-NorthEast-2024-04-24
Inside-Pier-2-Cofferdam-Top-of-Tremie-Seal-2024-04-01
Pier-4-Construction-2024-04-03
Class-I-Excavation-East-Side-to-River-2024-04-17
Thermoplastic-Pipe-Installation-for-Thompson-Run-Rd-2024-04-05

March 2024

Relocating-Drill-Rig-to-Pier-3-via-Floating-Barge-2024-03-07

WB-211-Pier-3-and-4-Construction-Looking-East-2024-03-01

SR-0018-Reconstruction-2024-03-12

Placement-of-Concrete-by-Tremie-for-Drilled-Shaft-at-Pier-3-2024-03-15

Excavation-Area-3-400-50-to-408-00-2024-03-07

Eacavation-at-Stations-400-50-to-408-00-T-635-2024-03-18

WB-211-Pier-1-Construction-2024-03-01

Relocating-Drill-Rig-to-Pier-3-via-Floating-Barge-2024-03-07
WB-211-Pier-3-and-4-Construction-Looking-East-2024-03-01
SR-0018-Reconstruction-2024-03-12
Placement-of-Concrete-by-Tremie-for-Drilled-Shaft-at-Pier-3-2024-03-15
Excavation-Area-3-400-50-to-408-00-2024-03-07
Eacavation-at-Stations-400-50-to-408-00-T-635-2024-03-18
WB-211-Pier-1-Construction-2024-03-01

February 2024

Excavation-for-Thompson-Run-Road-Relocation-2024-02-05

WB-211-Construction-Looking-West-2024-02-12

Selected-Borrow-Excavation-Rock-B-Station-215-00-I-76-WB-2024-02-14-17-35-53-2024-02-14

WB-212-Culvert-Extension-Construction-2024-02-12

East-Stormwater-Basin-Excavation-2024-02-12

REVISED-PHOTO-WB-212-Culvert-Extension-2024-02-12

Aerial-Photo-East-End-Earthwork-and-Widening-Looking-West-2024-02-21

Aerial-Photo-Interchange-Temp-A-Looking-North-2024-02-21

Excavation-for-Thompson-Run-Road-Relocation-2024-02-05
WB-211-Construction-Looking-West-2024-02-12
Selected-Borrow-Excavation-Rock-B-Station-215-00-I-76-WB-2024-02-14-17-35-53-2024-02-14
WB-212-Culvert-Extension-Construction-2024-02-12
East-Stormwater-Basin-Excavation-2024-02-12
REVISED-PHOTO-WB-212-Culvert-Extension-2024-02-12
Aerial-Photo-East-End-Earthwork-and-Widening-Looking-West-2024-02-21
Aerial-Photo-Interchange-Temp-A-Looking-North-2024-02-21

January 2024

WB-211-Pier-3-WB-Cofferdam-2024-01-18

Pier-Construction-Looking-East-2024-01-23

WB-211-Abutment 2-2024-01-05

Pier-Construction-Looking-West-2024-01-18

Class-C-Concrete-Mud-Mat-for-WB-212-Culvert-Extension-2024-01-08

Pier-1-EB-and-WB-2024-01-05

Earthwork-for-Mainline-Widening-East-End-of-Project-2024-01-05

East-Stormwater-Basin-Excavation-along-River-Road-2024-01-05

Permanent-Drainage-Installation-West-Access-Road-2024-01-08

Driving-Test-Piling-Abutment-1-2024-01-23

WB-211-Pier-3-WB-Cofferdam-2024-01-18
Pier-Construction-Looking-East-2024-01-23
WB-211-Abutment 2-2024-01-05
Pier-Construction-Looking-West-2024-01-18
Class-C-Concrete-Mud-Mat-for-WB-212-Culvert-Extension-2024-01-08
Pier-1-EB-and-WB-2024-01-05
Earthwork-for-Mainline-Widening-East-End-of-Project-2024-01-05
East-Stormwater-Basin-Excavation-along-River-Road-2024-01-05
Permanent-Drainage-Installation-West-Access-Road-2024-01-08
Driving-Test-Piling-Abutment-1-2024-01-23

December 2023

BRB-Pier-1-WB-Lift-3-Formwork-2023-12-07

Class-1-Excavation-Station-226-00-19-06-12-2023-12-12

Pier-3-WB-Test-Drilling-2023-12-08

River-Construction-Looking-East-2023-12-08

WB-211-Pier-1-Shaft-Construction-Progress-2023-12-12

WB-211-Pier-1-Shaft-Progress2-2023-12-14

WB-211-Pier-2-WB-Casing-Installation-2023-12-12

WB-211-WB-Abutment-2-Beam-Seat-Formwork-2023-12-12

BRB-Pier-1-WB-Lift-3-Formwork-2023-12-07
Class-1-Excavation-Station-226-00-19-06-12-2023-12-12
Pier-3-WB-Test-Drilling-2023-12-08
River-Construction-Looking-East-2023-12-08
WB-211-Pier-1-Shaft-Construction-Progress-2023-12-12
WB-211-Pier-1-Shaft-Progress2-2023-12-14
WB-211-Pier-2-WB-Casing-Installation-2023-12-12
WB-211-WB-Abutment-2-Beam-Seat-Formwork-2023-12-12

November 2023

72in-diameter-Endwall-BB-1-Installation-2-2023-11-09

BRB-Abutment-2-EB-Stem-Wall-Concrete-Pour-2023-11-15

I-76-Eastbound-Widening-Subbase-2023-11-06

I-76-Westbound-Excavation-and-Grading-for-Widening-2023-11-14

Pier-3-Cofferdam-Installation-2023-11-03

Piers-1-and-2-Construction-2023-11-03

River-Operations-2023-11-14

Temporary-Ramp-A-I-76-Eastbound-Ramps-to-SR-18-2023-11-20

Westbound-Widening-Subgrade-2023-11-08

Widening-Soil-Embankment-2023-11-15

72in-diameter-Endwall-BB-1-Installation-2-2023-11-09
BRB-Abutment-2-EB-Stem-Wall-Concrete-Pour-2023-11-15
I-76-Eastbound-Widening-Subbase-2023-11-06
I-76-Westbound-Excavation-and-Grading-for-Widening-2023-11-14
Pier-3-Cofferdam-Installation-2023-11-03
Piers-1-and-2-Construction-2023-11-03
River-Operations-2023-11-14
Temporary-Ramp-A-I-76-Eastbound-Ramps-to-SR-18-2023-11-20
Westbound-Widening-Subgrade-2023-11-08
Widening-Soil-Embankment-2023-11-15

October 2023

Inlet-Box-Placent-SR-0018-2023-10-10

Aerial-Photo-River-Construction-Progress-2-2023-10-25

Pier-1-WB-Stem-Lift-1-Curing-2023-10-24

Pile-Driving-WB-209-Abutment-2023-10-24

Form-Traveler-Construction-2023-10-16

Pier-2-WB-Footing-Excavation-2023-10-24

Aerial-Photo-West-Project-Limits-2023-10-25

60in-Pipe-Installation-SR-0018-2023-10-05

Project-Progress-Looking-West-2025-10-11

Aerial-Photo-Looking-West-to-East-2023-10-25

Aerial-Photo-Interchange-2023-10-25

Inlet-Box-Placent-SR-0018-2023-10-10
Aerial-Photo-River-Construction-Progress-2-2023-10-25
Pier-1-WB-Stem-Lift-1-Curing-2023-10-24
Pile-Driving-WB-209-Abutment-2023-10-24
Form-Traveler-Construction-2023-10-16
Pier-2-WB-Footing-Excavation-2023-10-24
Aerial-Photo-West-Project-Limits-2023-10-25
60in-Pipe-Installation-SR-0018-2023-10-05
Project-Progress-Looking-West-2025-10-11
Aerial-Photo-Looking-West-to-East-2023-10-25
Aerial-Photo-Interchange-2023-10-25

September 2023

48in-pipe-boring-2023-09-18

Aerial-Photo-East-Side-of-Beaver-River-2023-09-06

Aerial-Photo-West-Side-of-Beaver-River-2023-09-06

BRB-Pier-2-Trestle-Area-2023-09-12

Caisson-Cages-and-Shoring-Wall-at-Pier-4-2023-09-26

Concrete-Placement-for-Pier-1-Footing-2023-09-21

East-Basin-and-Thompson-Run-Road-Excavation-2023-09-26

Pier-1-Footing-Reinforcement-2023-09-18

Route-18-Median-Construction-2023-09-21

Setting-Spuds-Using-Vibratory-Pile-Driver-for-Cofferdam-2023-09-29

Stream-Mitigation-Channel-Construction-2023-09-11

Temporary-CSX-Railroad-Crossing-2023-09-26

48in-pipe-boring-2023-09-18
Aerial-Photo-East-Side-of-Beaver-River-2023-09-06
Aerial-Photo-West-Side-of-Beaver-River-2023-09-06
BRB-Pier-2-Trestle-Area-2023-09-12
Caisson-Cages-and-Shoring-Wall-at-Pier-4-2023-09-26
Concrete-Placement-for-Pier-1-Footing-2023-09-21
East-Basin-and-Thompson-Run-Road-Excavation-2023-09-26
Pier-1-Footing-Reinforcement-2023-09-18
Route-18-Median-Construction-2023-09-21
Setting-Spuds-Using-Vibratory-Pile-Driver-for-Cofferdam-2023-09-29
Stream-Mitigation-Channel-Construction-2023-09-11
Temporary-CSX-Railroad-Crossing-2023-09-26

August 2023

48in-Jack-and-Bore-Pipe-Installation-2023-08-08

Construction-along-River-Road-2023-08-25

Contractor-Laydown-Area-West-Side-of-River-2023-08-30

East-Side-of-River-Looking-West-2023-08-22

Existing-Beaver-River-Bridge-from-West-River-Bank-2023-08-10

Hydroseeding-along-River-Road-2023-08-08

Installation-of-54in-RCP-2023-08-21

Milling-of-Existing-Aspalt-Pavement-2023-08-25

Pier-1-Caisson-Rebar-and-Formwork-2023-08-16

Rebar-Installation-for-Pier-1-Footings-2023-08-30

Setting-20ft-Section-of-Casing-for-48in-Jack-and-Bore-Pipe-2023-08-17

Setting-Endwall-2023-08-17

WB-211-Abutment-2-Completed-Footings-2023-08-09

Western-Limit-of-Project-2023-08-28

48in-Jack-and-Bore-Pipe-Installation-2023-08-08
Construction-along-River-Road-2023-08-25
Contractor-Laydown-Area-West-Side-of-River-2023-08-30
East-Side-of-River-Looking-West-2023-08-22
Existing-Beaver-River-Bridge-from-West-River-Bank-2023-08-10
Hydroseeding-along-River-Road-2023-08-08
Installation-of-54in-RCP-2023-08-21
Milling-of-Existing-Aspalt-Pavement-2023-08-25
Pier-1-Caisson-Rebar-and-Formwork-2023-08-16
Rebar-Installation-for-Pier-1-Footings-2023-08-30
Setting-20ft-Section-of-Casing-for-48in-Jack-and-Bore-Pipe-2023-08-17
Setting-Endwall-2023-08-17
WB-211-Abutment-2-Completed-Footings-2023-08-09
Western-Limit-of-Project-2023-08-28

July 2023

Shotcrete-Placement-at-East-Access-Road-Shoring-2023-07-11

Pier-1-Cassion-Drilling-2023-07-13

Drilling-for-Pier-1-Caissons-2023-07-12

Pier-1-Cassion-Rebar-Installation-2023-07-13

Concrete-Placement-for-Pier-1-Caissons-2023-07-31

WB-211-Abutment-2-Footing-Rebar-and-Formwork-2023-07-13

24in-Thermoplastic-Pipe-Installation-2023-07-11

72in-Pipe-Boring-2023-07-11

WB-211-Abut-2-WB-Pile-Driving-2023-07-11

CSX-Temporary-Rail-Crossing-Installation-2023-07-31

East-Side-of-Beaver-River-Looking-West-2023-07-27

Inside-of-72in-Jack-and-Bore-Pipe-Tunneling-2023-07-11

Shotcrete-Placement-at-East-Access-Road-Shoring-2023-07-11
Pier-1-Cassion-Drilling-2023-07-13
Drilling-for-Pier-1-Caissons-2023-07-12
Pier-1-Cassion-Rebar-Installation-2023-07-13
Concrete-Placement-for-Pier-1-Caissons-2023-07-31
WB-211-Abutment-2-Footing-Rebar-and-Formwork-2023-07-13
24in-Thermoplastic-Pipe-Installation-2023-07-11
72in-Pipe-Boring-2023-07-11
WB-211-Abut-2-WB-Pile-Driving-2023-07-11
CSX-Temporary-Rail-Crossing-Installation-2023-07-31
East-Side-of-Beaver-River-Looking-West-2023-07-27
Inside-of-72in-Jack-and-Bore-Pipe-Tunneling-2023-07-11

June 2023

west-access-road-sediment-trap-construction-2023-06-03

west-access-road-2023-06-03

west-end-of-mainline-bridge-facing-east-2023-06-21

wb-211-abutment-1-fill-2023-06-03

60in-pipe-installation-at-future-interchange-2023-06-21

placing-asphalt-for-temporary-pavement-mainline-2023-06-16

wb-211-wb-abut-2-pile-driving-2023-06-20

east-access-road-2023-06-21

existing-mainline-temporary-shoring-2023-06-03

wb-211-pier-1-caisson-drilling-2023-06-01

pier-1-soil-nail-shoring-wall-2023-06-21

west-access-road-sediment-trap-construction-2023-06-03
west-access-road-2023-06-03
west-end-of-mainline-bridge-facing-east-2023-06-21
wb-211-abutment-1-fill-2023-06-03
60in-pipe-installation-at-future-interchange-2023-06-21
placing-asphalt-for-temporary-pavement-mainline-2023-06-16
wb-211-wb-abut-2-pile-driving-2023-06-20
east-access-road-2023-06-21
existing-mainline-temporary-shoring-2023-06-03
wb-211-pier-1-caisson-drilling-2023-06-01
pier-1-soil-nail-shoring-wall-2023-06-21

May 2023

2023-05-04 Aerial Photo Beaver Valley Interchange

2023-05-22 West Access Road 1 Viewing From Top

2023-05-22 South End of Bridge Thompson Run Road & East Access Road

2023-05-22 West Access Road 1 Viewing From Top

2023-05-22 West Access Road 1 Viewing From Top

2023-05-22 South End of Bridge Thompson Run Road & East Access Road

2023-05-22 West Access Road 1 Viewing From Top

2023-05-16 Pre-Drilling for Piling

2023-05-22 South End of Bridge Thompson Run Road & East Access Road

2023-05-04 South End of Bridge East Side E&S Control

2023-05-04  North End of Bridge East Side Looking South

2023-05-04 Aerial Photo Beaver Valley Interchange
2023-05-22 West Access Road 1 Viewing From Top
2023-05-22 South End of Bridge Thompson Run Road & East Access Road
2023-05-22 West Access Road 1 Viewing From Top
2023-05-22 West Access Road 1 Viewing From Top
2023-05-22 South End of Bridge Thompson Run Road & East Access Road
2023-05-22 West Access Road 1 Viewing From Top
2023-05-16 Pre-Drilling for Piling
2023-05-22 South End of Bridge Thompson Run Road & East Access Road
2023-05-04 South End of Bridge East Side E&S Control
2023-05-04  North End of Bridge East Side Looking South

April 2023

West-End-of-Bridge-Looking-East-02-2023-04-12

Aerial-Photo-West-Access-Road-2023-04-13

North-End-of-Bridge-East-Side-02-2023-04-12

North-End of-Bridge-Looking-South-4-2023-04-12

North-End-of-Bridge-04-2023-04-12

West-Access-Road-Looking-East-01-2023-04-12

Thompson-Run-Road-Looking-West-2023-04-26

West-End-Bridge-Looking-East-01-2023-04-21

East-End-of-Bridge-East-Side-E-S-Control-2023-04-12

Pre-Drill-Piles-WB209a-abut-2-2023-04-14

West-Access-Road-Earthwork-2023-04-04

North-End-of-Bridge-01-2023-04-12

West-End-of-Bridge-Looking-East-02-2023-04-12
Aerial-Photo-West-Access-Road-2023-04-13
North-End-of-Bridge-East-Side-02-2023-04-12
North-End of-Bridge-Looking-South-4-2023-04-12
North-End-of-Bridge-04-2023-04-12
West-Access-Road-Looking-East-01-2023-04-12
Thompson-Run-Road-Looking-West-2023-04-26
West-End-Bridge-Looking-East-01-2023-04-21
East-End-of-Bridge-East-Side-E-S-Control-2023-04-12
Pre-Drill-Piles-WB209a-abut-2-2023-04-14
West-Access-Road-Earthwork-2023-04-04
North-End-of-Bridge-01-2023-04-12

March 2023

2023-03-23 Thompson Run Road Looking West

2023-03-20 BRB Embankment 262+14 to 265+50 WB

2023-03-23 CSX Railroad Looking East

2023-03-17 BRB Thompson Run Road Ditch Improvement

2023-03-14 BRB West Access Road Class 1 Excavation 20+00

2023-03-01 BRB View of Project Work NE & NW from Thompson Run Road

2023-03-23 Thompson Run Road Looking West
2023-03-20 BRB Embankment 262+14 to 265+50 WB
2023-03-23 CSX Railroad Looking East
2023-03-17 BRB Thompson Run Road Ditch Improvement
2023-03-14 BRB West Access Road Class 1 Excavation 20+00
2023-03-01 BRB View of Project Work NE & NW from Thompson Run Road

February 2023

2023-02-22 Thompson Run Road Looking West

2023-02-17 BRB Clearing Ramp ''J'' Abutment 1

2023-02-24 East End of Bridge Looking West

2023-02-06 BRB Excavation & Clearing for West Access Road

2023-02-10 BRB Placing Embankment Material West Access Road 4+00 to 5+00

2023-02-15 BRB Clearing West Access Road

2023-02-22 Thompson Run Road Looking West
2023-02-17 BRB Clearing Ramp ''J'' Abutment 1
2023-02-24 East End of Bridge Looking West
2023-02-06 BRB Excavation & Clearing for West Access Road
2023-02-10 BRB Placing Embankment Material West Access Road 4+00 to 5+00
2023-02-15 BRB Clearing West Access Road

Completed Construction

Map of excess excavation areas
Map of excess excavation areas
Replacement of the Bridge No. WB-210A at Milepost 12.76 in Beaver County, Pennsylvania. This project consisted of replacing a 3-span steel stringer bridge with a single span temporary bridge, the design/build installation of a retaining wall, the design/build modification of the ramp highway lighting and the realignment of Ramp B over SR 0018 (Big Beaver Boulevard). The project was completed in mid-2014.
Map of excess excavation areas
Map of excess excavation areas
Replacement of Bridge No. WB-207, a single span thru-truss railroad structure carrying Norfolk Southern Railroad over the Pennsylvania Turnpike with a 2-span thru-girder structure.
Map of excess excavation areas
Map of excess excavation areas

Replacement of Bridge No. WB-208, a single span thru-girder railroad structure carrying Norfolk Southern Railroad over the Pennsylvania Turnpike with a 2-span thru-girder structure; to construct PP 12.58 Eastbound, a post and plank retaining wall; and to construct two railroad roadbeds and associated drainage features.

Map of excess excavation areas
Map of excess excavation areas

This project provided for the replacement of four (4) spans of the existing WB-206 structure over the Turnpike (The Homewood Viaduct) with (3) spans. The existing spans consist of one concrete T-beam span, one steel girder span, one concrete slab span and one concrete box beam span. The project also includes installation of a sanitary sewer and water lines, and realigning approximately 1,650 ft of Foxwood Road (T-655).

More Project Resources

Project Overview

Learn about Milepost 12-14 Total Reconstruction.

Learn More

News & Public Involvement

Learn how we stay connected with the public about this project.

Stay Updated

Team & Contact Information

Learn about the team that we will work with to complete the work on this project.

Contact the Team

  • About Us
    • Our Mission
    • Our Board of Commissioners
    • Commission Meeting Information
    • Our Executive Leadership
    • Design & Construction
    • PA Turnpike History
    • Investor Relations
    • Resource Library
    • Policies & Standards
    • Security & Fraud
    • About Us FAQs
  • News
    • Traffic Reports
    • The Road Ahead: Turnpike Newsletter
    • Stories from the Turnpike
    • Media Center
    • PA Turnpike Blogs
    • Right to Know Request
    • Law Enforcement Requests
    • Vehicle Registration Suspension Appeals
  • Responsibility Matters
    • Sustainability
    • Clean Water
    • Accountability
    • PA Mobility Partnership Reports
    • National Center for Missing and Exploited Children
    • Human Trafficking Awareness
  • Contract/PO Search
  • Careers
  • Contact Us
  • Site Map
  • Employee Login
  • Facebook
  • Twitter
  • Instagram
  • Linkedin
  • YouTube

©2025 The Pennsylvania Turnpike Commission