Wetland Mitigation Site

I-95 Interchange - 2012

Back to Completed Construction

Project Description

As part of the I-95 Interchange Project, there are some unavoidable impacts to existing wetlands and streams. In order to provide mitigation for these impacts the Turnpike has constructed new wetlands and streams on a 37-acre parcel of land which is located at the intersection of Zimmerman Lane and Newportville Road in Middletown Township.

The site is on a parcel of land owned by the Turnpike. The details of the construction have been closely coordinated with all the required environmental agencies including the Pennsylvania Department of Environmental Protection, Bucks County Conservation District and the Army Corps of Engineers.

The project included construction of 3 acres of wetlands and 3 small streams. The Turnpike acquired the site during earlier studies to construct the new interchange. The site was proposed for development of a mobile home park, however, the area is now restored by removal of the development infrastructure and construction of the wetlands and streams.

The mitigation project's intent is to provide a diverse wetland environment that fosters wildlife habitat, water quality enhancement and floodwater retention.

Project Schedule

Construction began in April 2012 and was completed in November 2012.

Construction Status

February/March 2013

  • All construction completed. Vegetation is now in maintenance/monitoring period.

Image Gallery

Construction Information Archive

January 2013

  • All construction completed. Vegetation is now in maintenance/monitoring period.

November/December 2012

  • Shrub and tree plantings are now in maintenance period.

October 2012

  • Shrub and tree plantings are now in maintenance period.

September 2012

  • The vegetation installed in July/August continues to germinate and grow.
  • Shrub and tree planting is completed.

August 2012

  • Vegetation recently installed continues to germinate and grow.
  • Plantings scheduled for installation in September due to seasonal weather considerations.

July 2012

  • Stage 3 area new stream channel installations have been completed.
  • Stage 3 area grading and seeding was completed.
  • Plantings scheduled for installation in September due to seasonal weather considerations.

June 2012

  • Installation of new stream channel in Stage 2 area was completed.
  • Stage 2 area grading and seeding was completed.
  • Stage 3 area grading started, completion anticipated in mid-July 2012.
  • Wetland plantings scheduled for September due to seasonal weather considerations.

May 2012

  • The contractor maintained the previously installed erosion and sedimentation controls.
  • Tree and vegetation clearing was completed.
  • Stage 2 site grading started and is approximately 50% complete.

April 2012

  • The contractor mobilized to the site and installed erosion and sedimentation controls.
  • Clearing existing vegetation is ongoing and wetland grading is anticipated to begin in mid-May 2012.
  • Stage 1 removal of ground vegetation and seeding was completed.

More Project Resources

Project Overview

Learn about I-95 Interchange Project.

Learn More

News & Public Involvement

Learn how we stay connected with the public about this project.

Stay Updated

Team & Contact Information

Learn about the team that we will work with to complete the work on this project.

Contact the Team