Section D10/East

Turnpike Widening to Delaware River Bridge

Back to Completed Construction

Project Description

As the first contract for construction of the I95/I276 Interchange connection, Section D10 will widen the Pennsylvania Turnpike Mainline (I276) between the existing I95 roadway and the Delaware River Bridge. The project will include construction of the new Northbound I95 “flyover” structure, which will connect I95 Northbound to I276 Eastbound.

In order to provide sufficient room for the merging of the two roadways, Section D10 consists of widening and reconstruction of approximately 1½ miles of existing I276.

This project also includes:

  • Replacement/construction of new wider bridges over Durham Road, Route 413 and Mill Creek
  • Construction of retaining walls along both eastbound and westbound PA Turnpike Mainline due to widening of the existing roadway
  • Sound barrier walls along both eastbound and westbound areas of the project
  • Replacement/reconstruction of the existing roadways
  • Installation of new drainage systems, construction of basins for erosion control and storm water management
  • Replacement of signing and guide rail
  • Installation of ITS facilities
  • Improvements to local roadways include Durham Road and Route 413 in the vicinity of I276.

Project Schedule

The project schedule anticipates work to begin in the fall of 2014 and continue thru the 2017 construction season.

Construction Status

September 2018 project completed.

Videos

Image Gallery

Construction Information Archive

July/August 2018

  • Continued converting basins.
  • Continued performing punch list items.

June 2018

  • Began converting basins.
  • Continued performing punch list items.

April/May 2018

  • Continued applying permanent pavement markings.
  • Continued performing punch list items.

March 2018

  • Started applying permanent pavement markings.
  • Began performing punch list items.

February 2018

  • Continued constructing concrete islands/sidewalk along Durham and New Rodgers Roads.
  • Continued installing right-of-way fence.
  • Switched traffic to Final Lane Configuration on I-276.

January 2018

  • Constructed concrete islands/sidewalk along Durham and New Rodgers Roads.
  • Installed right-of-way fence.
  • Switched traffic to Final Lane Configuration on I-276.

December 2017

  • Continued erecting fencing on top of bridge parapet on northbound I-95 flyover bridge.
  • Continued groove/grinding of concrete decks for mainline and flyover bridges.
  • Continued placing subbase and bituminous paving on northbound I-95 Flyover ramp to eastbound I-276.
  • Continued setting precast single face barrier, glare screen barrier and cast-in-place transitions adjacent to the eastbound and westbound I-276 roadway.
  • Placed bituminous paving for Stage 3 median portion of the eastbound and westbound I-276 roadway from the northbound on-ramp to the DVI Interchange.
  • Continued roadwork along Durham and New Rodgers Roads.
  • Continued mill/overlay of existing I-276 pavement.
  • Switched traffic to Final Lane Configuration.

October/November 2017

  • Continued forming and pouring of cast-in-place bridge parapet on northbound I-95 flyover bridge.
  • Began erecting fencing on top of bridge parapet on northbound I-95 flyover bridge.
  • Started painting the bridge parapet on northbound I-95 flyover bridge.
  • Began groove/grinding of concrete decks for mainline and flyover bridges.
  • Started placement of subbase and bituminous paving on northbound I-95 flyover ramp to eastbound I-276.
  • Constructed bridge parapet on the middle portion of I-276 bridge over Mill Creek.
  • Removed pavement, installed drainage pipe, graded and placed subbase of the Stage 3 median portion of the eastbound and westbound I-276 roadway from I-95 to the DVI Interchange.
  • Set precast single face barrier, glare screen barrier and cast-in-place transitions adjacent to the eastbound and westbound I-276 roadway.
  • Began placement of bituminous paving for Stage 3 median portion of the eastbound and westbound I-276 roadway from I-95 to the DVI Interchange.
  • Continued roadwork along Durham and New Rodgers Roads.
  • Continued painting retaining walls, sound barrier walls and bridge substructure.
  • Continued installing light poles
  • Continued topsoil, seeding, and planting on north side of project.
  • Continued erecting sign structures.
  • Started mill/overlay of existing I-276 pavement.
  • Switched traffic to Final Configuration.

August/September 2017

  • Started construction of bridge approach slab and parapet of the proposed westbound/eastbound I-276 bridge over New Rodgers Road.
  • Continued construction of bridge approach slabs and parapet of the proposed westbound/eastbound I-276 bridge over Durham Road.
  • Began forming and pouring of cast-in-place bridge parapet on northbound I-95 flyover bridge.
  • Started the differential barrier between Durham Road and New Rodgers Road bridges.
  • Placed single face barrier and moment slabs on northbound I-95 flyover ramp to eastbound I-276.
  • Continued construction with differential barrier at base of I-95 flyover ramp adjacent to westbound roadway.
  • Began bituminous paving of westbound I-276 roadway of the middle portion of the project.
  • Started drainage pipe installation along westbound I-276 roadway.
  • Placed permanent glare screen and single face barrier along the westbound roadway.
  • Installed guiderail adjacent to westbound I-276 roadway.
  • Started to implement Stage 3 traffic switch to westbound I-276 lanes.
  • Began demolition, pile driving, substructure and deck construction of the middle portion of I-276 bridge over Mill Creek.
  • Started pavement removal, installation of drainage pipe, grading and placement subbase of the median portion of the I-276 roadway east and west of the I-276 bridge over Mill Creek.
  • Erected panels for sound barrier walls adjacent to eastbound I-276.
  • Began bituminous paving of Durham and New Rodgers Roads.
  • Continued painting retaining walls, sound barrier walls and bridge substructure.
  • Installed light poles
  • Continued topsoil, seeding, and planting on north side of project.
  • Erected Sign Structures

June/July 2017

  • Continued deck construction for the new westbound/eastbound I-276 bridge over New Rodgers Road.
  • Began construction of bridge approach slabs and parapet underway for the new westbound/eastbound I-276 bridge over Durham Road.
  • Continued installing deck forms and deck reinforcement for the northbound I-95 flyover bridge from Pier 10 to Abutment No. 2.
  • Continued concrete deck pour of the northbound I-95 flyover bridge from Abutment No. 1 to Pier 4 and from Pier 10 to Abutment No. 2.
  • Began forming and pouring of bridge parapet on northbound I-95 flyover.
  • Started installing precast barrier and moment slab on top of T-Wall.
  • Implemented westbound roadway crossover.
  • Began placement and grading of subbase for westbound I-276 roadway at the center of the project.
  • Continued bituminous paving of the westbound I-276 roadway at the east and west ends of the project.
  • Erected posts and panels for sound barrier walls adjacent to westbound I-276.
  • Installed precast barrier for eastbound approach from northbound I-95 flyover bridge.
  • Demolished existing median deck and substructure of westbound I-276 bridge over Mill Creek.
  • Started predrill for pile foundation at I-276 over Mill Creek.
  • Started realignment of Mill Creek-Stage 2
  • Continued installing signal foundations along Durham Road.
  • Began placement and grading of subbase along New Rodgers Road.
  • Started topsoil, seeding, and planting on north side of project.
  • Continued painting sound barrier walls and substructure surfaces.

May 2017

  • Continued deck construction of the proposed westbound I-276 bridges over Durham Road and New Rodgers Road.
  • Began concrete deck pour of the northbound I-95 flyover bridge from Abutment No. 1 to Pier 4.
  • Installed deck forms and deck reinforcement for the northbound I-95 flyover bridge from Pier 10 to Abutment No. 2.
  • Formed, poured cast-in-place wall, set T-Wall precast segments and backfill adjacent to westbound I-276 roadway.
  • Continued erection of posts and panels for ground mounted sound barrier walls adjacent to westbound I-276.
  • Backfilled MSE walls for eastbound approach from the northbound I-95 flyover bridge.
  • Constructed parapet/approach slab for westbound I-276 bridge over Mill Creek.
  • Placed and graded subbase along east half of westbound roadway.
  • Began bituminous paving along east half of westbound roadway.
  • Continued installing signal foundations along Durham Road.
  • Started bituminous paving of widening Durham Road and grading of New Rodgers Road.
  • Graded subbase of westbound I-276 bridge from Durham Road to I-95.
  • Began painting sound barrier walls and substructure surfaces.

April 2017

  • Continued deck construction of the proposed westbound I-276 bridges over Durham Road and New Rodgers Road.
  • Installed tendons at Pier 2 for post tensioning of the integral cap for the northbound I-95 flyover bridge.
  • Installed deck reinforcement for the northbound I-95 flyover bridge from Abutment No. 1 to Pier 4.
  • Installed overhangs and stay in place forms for the northbound I-95 flyover bridge from Abutment No. 2 to Pier 10.
  • Formed and poured cast-in-place wall and set T-Wall precast segments adjacent to westbound I-276 roadway.
  • Erected posts and panels for ground mounted sound barrier walls adjacent to westbound I-276.
  • Built parallel MSE walls for eastbound approach from northbound I-95 flyover bridge.
  • Continued deck construction/Pour deck for westbound I-276 bridge over Mill Creek.
  • Continued placing embankment and rough grade of westbound I-276 roadway.
  • Continued installing signal foundations along Durham Road.
  • Continued installing sign structure foundations.
  • Continued installing drainage inlets and pipes along westbound I-276 roadway.

March 2017

  • Started deck construction of the proposed westbound I-276 bridges over Durham Road and New Rodgers Road.
  • Poured Pier 2 Integral Cap for the northbound I-95 flyover bridge.
  • Installed overhangs for the northbound I-95 flyover bridge from Abutment No. 1 to Pier 4.
  • Erected structural steel girders for the northbound I-95 flyover bridge from Abutment No. 2 to Pier 10.
  • Began excavation/foundation of cast-in-place wall and T-Wall adjacent to westbound I-276.
  • Drilled/poured caissons for ground mounted sound barrier walls adjacent to westbound I-276.
  • Continued building parallel MSE walls for eastbound approach from the northbound I-95 flyover bridge.
  • Started deck construction for westbound I-276 bridge over Mill Creek.
  • Continued placing embankment and rough grade of westbound I-276 roadway.
  • Continued installing signal foundations along Durham Road.
  • Started installing sign structure foundations.
  • Continued installing drainage inlets and pipes along westbound I-276 roadway.

January/February 2017

  • Continued construction of the proposed westbound I-276 bridges over Durham Road and New Rodgers Road.
  • Built the remaining pier substructures for the northbound I-95 flyover bridge.
  • Erected structural steel girders for the northbound I-95 flyover from Abutment No. 1 to Pier 4.
  • Began erection of structural steel girders for the northbound I-95 flyover from Abutment No. 2 to Pier 10.
  • Started building Integral Pier Cap for the northbound I-95 flyover bridge.
  • Placed precast barrier and moment slabs for T-Walls adjacent to westbound I-276.
  • Drilled and poured caissons for ground mounted sound barrier walls adjacent to westbound I-276.
  • Started building parallel MSE walls along eastbound approach from northbound I-95 flyover bridge.
  • Began construction of abutments for westbound I-276 bridge over Mill Creek.
  • Placed embankment and rough grade of westbound I-276 roadway.
  • Installed signal foundations along Durham Road.
  • Installed drainage inlets and pipes along westbound I-276.

November/December 2016

  • Began construction of the proposed westbound I-276 bridges over Durham Road and New Rodgers Road.
  • Set precast beams for the westbound I-276 bridge over Durham Road.
  • Built the remaining abutment and pier substructure for the northbound I-95 flyover bridge.
  • Erected structural steel girders for the northbound I-95 flyover from Abutment No. 1 to Pier 4.
  • Constructed bridge parapet for the southbound I-95 bridge adjacent to Mill Creek.
  • Placed precast concrete segments and precast barrier for T-Walls adjacent to westbound I-276.
  • Drilled caisson for ground mounted sound barrier walls adjacent to westbound I-276.
  • Demolished existing westbound I-276 bridge over Mill Creek.
  • Began pile driving for the proposed westbound I-276 bridge over Mill Creek.
  • Continued building bridge superstructure on six spans of northbound I-95 flyover bridge.
  • Excavated, placed embankment and started subbase for westbound I-276 roadway widening.
  • Installed drainage inlets and pipes along westbound I-276.

September/October 2016

  • Demolished existing westbound I-276 bridge over New Rodgers Road.
  • Completed excavation of abutment foundation for proposed westbound I-276 bridges over Durham Road and New Rodgers Road.
  • Conducted pile driving for proposed westbound I-276 bridges over Durham Road and New Rodgers Road.
  • Constructed foundation and walls for proposed westbound I-276 bridges over Durham Road and New Rodgers Road.
  • Erected precast concrete segments for T-Wall adjacent to westbound I-276.
  • Conducted pile driving at pier foundations for northbound I-95 Flyover Bridge.
  • Erected precast beams on three additional spans of northbound I-95 Flyover Bridge.
  • Completed construction of bridge superstructure on six spans of northbound I-95 Flyover Bridge.
  • Completed concrete deck pour for four spans of the southbound I-95 bridge adjacent to Mill Creek.
  • Excavated and placed embankment for westbound I-276 roadway widening.
  • Demolished existing I-276 bridge over Mill Creek.

August 2016

  • Completed bituminous paving along eastbound I-276 roadway widening in preparation for traffic switch.
  • Installed sound barrier steel posts and concrete panels along eastbound I-276 roadway widening.
  • Opened new eastbound off-ramp to Route 13.
  • Switched eastbound/westbound traffic to the eastbound I-276 roadway widening.
  • Continued construction of pier structures for northbound I-95 flyover bridge.
  • Erected precast beams on three additional spans of northbound flyover bridge.
  • Started building bridge superstructure on six spans of northbound I-95 flyover bridge.
  • Completed concrete deck pour for four spans of the southbound I-95 bridge adjacent to Mill Creek.
  • Started backfilling southbound I-95 bridge adjacent to Mill Creek.
  • Demolished existing westbound I-276 bridge over Durham Road.
  • Removed existing concrete pavement along westbound I-276 roadway.
  • Excavated and placed embankment for westbound I-276 roadway widening.
  • Excavated and constructed footing for T-Wall adjacent to westbound I-276 roadway widening.

July 2016

  • Continued construction of pier caps for northbound I-95 flyover bridge.
  • Continued building bridge decks on three spans of northbound I-95 flyover bridge.
  • Placed four span concrete deck pour for southbound I-95 bridge adjacent to Mill Creek.
  • Installed remaining precast barrier and moment slabs on top of T-Walls along eastbound I-276 roadway widening.
  • Installed sound barrier steel posts and concrete panels along eastbound I-276 roadway widening.
  • Continued bituminous paving, base and binder courses, along eastbound I-276 roadway widening.
  • Tied in new off-ramp with existing off-ramp to Route 13.
  • Installed overhead lighting poles along the eastbound I-276 roadway widening.
  • Applied architectural color coatings on concrete surface of precast barrier and soundwalls.
  • Placed embankment for westbound I-276 widening.

June 2016

  • Continued construction of pier caps for northbound I-95 flyover bridge.
  • Continued building bridge decks on three spans of northbound I-95 flyover bridge.
  • Prepared four span concrete pour for southbound I-95 bridge adjacent to Mill Creek.
  • Poured approach slabs for I-276 Mainline Bridge over Durham Road.
  • Installed remaining precast barrier and moment slabs on top of T-Walls along eastbound I-276 roadway widening.
  • Installed sound barrier steel posts and concrete panels along eastbound I-276 roadway widening.
  • Continued grading of subgrade and subbase in preparation for bituminous paving of remaining eastbound I-276 roadway widening.
  • Began bituminous paving for the eastbound I-276 roadway widening.
  • Placed subbase for the relocated off-ramp to Route 13
  • Installed overhead lighting poles along the eastbound I-276 roadway widening.
  • Applied architectural color coatings on outside of T-Walls.
  • Placed embankment for westbound I-276 widening.

May 2016

  • Continued construction of pier caps for northbound I-95 flyover bridge.
  • Started building of bridge decks on three spans of northbound I-95 flyover bridge.
  • Continued placement of deck reinforcement for four span concrete pour for southbound I-95 bridge adjacent to Mill Creek.
  • Poured single span concrete deck pour for the PA Turnpike Mainline bridge over Durham Road.
  • Continued installation of precast barrier on top of T-Walls along eastbound I-276 roadway widening.
  • Started installation of moment slabs adjacent to precast barrier along eastbound I-276 roadway.
  • Continued installation of sound barrier steel posts and concrete panels along eastbound I-276 roadway widening.
  • Continued grading of subgrade and subbase in preparation for bituminous paving of the eastbound I-276 widening.
  • Continued placement of structural fill and subsequent of construction at bridge approaches.
  • Started landscape plantings behind walls along eastbound I-276 roadway widening.
  • Continued applying architectural color coatings on outside of T-Walls.

April 2016

  • Continued construction of pier caps for northbound I-95 flyover bridge.
  • Erected precast beams on three spans of northbound I-95 flyover bridge.
  • Placed deck reinforcement for four span bridge concrete for southbound I-95 bridge adjacent to Mill Creek.
  • Continued preparation for single span concrete deck pour for the PA Turnpike Mainline bridge over Durham Road.
  • Poured single span deck for the PA Turnpike Mainline bridge over New Rodgers Road.
  • Continued installation of precast barrier on top of T-Walls along eastbound I-276 roadway widening.
  • Applied architectural color coatings on outside of T-Walls.
  • Continued installation of sound barrier steel posts and concrete panels along eastbound I-276 roadway widening.
  • Started installation of drainage pipe along eastbound I-276 roadway widening.
  • Continued ongoing placement and grading of subgrade and corresponding subbase in preparation for paving the eastbound I-276 widening.
  • Placed structural fill at bridge approaches.

January/February/March 2016

  • Started construction of pier caps for the northbound I-95 flyover bridge.
  • Started construction for the concrete pour for the southbound I-95 flyover bridge adjacent to Mill Creek.
  • Erected precast bulb tee beams on the PA Turnpike Mainline bridges over Durham and New Rodgers roads.
  • Continued T-Wall construction and backfilling along eastbound I-276 roadway widening.
  • Completed installation of sound barrier wall caissons and steel posts along eastbound I-276 roadway widening.
  • Began placement of precast barrier on T-Walls along eastbound I-276 roadway widening.
  • Completed placement of earthwork embankment and grading of subbase for eastbound I-276 widening.

November/December 2015

  • Continued installation of foundations and pier columns for the northbound I95 flyover bridge. Installed new bridge beams for the Mill Creek structure.
  • Continued construction of rock/soil embankments along eastbound PA Turnpike Mainline widening area and continued installation of retaining walls to support the future widening.
  • Continued installing support of excavation and construction of new bridge foundations for mainline bridges at Durham Road and Route 413. New bridge beams installed for eastbound PA Turnpike Mainline widening area over Route 413.

September/October 2015

  • Installation of foundations and pier columns for the northbound fly over bridge continued
  • Installed new bridge beams for the Mill Creek structure
  • Continued construction of rock/soil embankments along eastbound widening area and continued installation of retaining walls to support the future widening
  • Continued excavation for, and construction of, new bridge foundations for PA Turnpike Mainline bridges at Durham Rd and Route 413

August 2015

  • Continued installation of foundation and pier columns for the northbound I95 flyover bridge. Contractor installed new bridge beams for the Mill Creek structure.
  • Continued construction of rock/soil embankment along eastbound PA Turnpike Mainline widening area and continued installation of retaining walls to support the future widening.
  • Continued installing support of excavation and construction of new bridge foundations for mainline bridges at Durham Road and Route 413.

July 2015

  • Continued installation of foundation and pier columns for the northbound I95 flyover bridge. Contractor preparing for installation of new bridge beams for the Mill Creek structure.
  • Continued construction of rock/soil embankment along eastbound PA Turnpike Mainline widening area and started installation of retaining walls to support the future widening.
  • Continued installing support of excavation and demolishing existing mainline bridges at Durham Road and Route 413.

May/June 2015

  • Continued installation of foundation and pier columns for the northbound I95 flyover bridge.
  • Continued construction of rock/soil embankment along eastbound PA Turnpike Mainline widening area.
  • Continued installing support of excavation and demolishing existing mainline bridges at Durham Road and Route 413.

March/April 2015

  • Completed clearing of trees along eastbound PA Turnpike Mainline from Route 413 to the Route 13 exit.
  • Continued installation of foundation piles and pier columns for the northbound I95 fly over bridge.
  • Continued construction of rock embankment along eastbound PA Turnpike Mainline just east of Route 413.
  • Started placement of concrete for new Mill Creek bridge foundations.

January/February 2015

  • Continued installation of foundation piles for the northbound fly over bridge.
  • Continued clearing of trees along eastbound PA Turnpike Mainline from Route 413 to the Route 13 exit.
  • Continued construction of rock embankment along eastbound PA Turnpike Mainline just east of Route 413.
  • Started placement of concrete for new Mill Creek Bridge foundations.

December 2014

  • Continued installation of foundation piles for the northbound fly over bridge.
  • Continued clearing of trees along eastbound PA Turnpike Mainline from Route 413 to the Route 13 exit.
  • Continued construction of rock embankment along eastbound PA Turnpike Mainline just east of Route 413.

November 2014

  • Installation of the sandbag cofferdam and Phase 1 relocation of Mill Creek was completed.
  • Completed construction of Basin M1 on the eastbound PA Turnpike Mainline.
  • Installation of foundation piles for the northbound flyover bridge was started.
  • Clearing trees at east end for construction of new eastbound off ramp at Route 13.
  • Started construction of rock embankment eastbound PA Turnpike Mainline just east of Route 413.

October 2014

  • Contractor mobilized to the project site.
  • Started installation of Erosion and Sedimentation controls.
  • Started installation of sandbag cofferdam and relocation of Mill Creek.
  • Started construction of basin M1 on eastbound PA Turnpike Mainline.

More Project Resources

Project Overview

Learn about I-95 Interchange Project.

Learn More

News & Public Involvement

Learn how we stay connected with the public about this project.

Stay Updated

Team & Contact Information

Learn about the team that we will work with to complete the work on this project.

Contact the Team