Project Overview
This project is for concrete pavement repairs to the existing ramps and main Connector of the interchange. Work will also include structure guiderail approach modification, drainage upgrades, bridge barrier concrete patching, inlet repairs, guiderail upgrades, shoulder stabilization, permanent pavement markings, delineation, and post mounted signs. Maintenance and Protection of interchange traffic is also included.
Project construction activities started on Monday, July 24, 2023. Project completion date is October 17, 2025.
There are four phases to the project.
Phase 1 included Ramp M, Ramp P, and Loop A which were completed during the 2023 construction season.
Phases 2 through 3 included Ramp J, Ramp JK, Ramp K, Ramp L, Ramp R, Loop B, and Structure S-23394 work were completed during the 2024 construction season.
Phase 4 will be completed in 2025 which includes the Eastbound Connector Road, Westbound Connector Road, Ramp A, Ramp B, Ramp N, for Concrete Pavement Patching, Pavement Markings, Signage, and ancillary cleanup work There will be some detouring of traffic during construction.
Project Schedule
Construction continues work on the project Monday through Thursday working night shift from 7:00 PM to 6:00 AM through Friday, May 9, 2025, to install measures for the Ramp D Detour.
Monday, May 12, 2025 through May 16, 2025: Work will occur on Ramp A and Ramp C with a detour. The detour will start around 6:00 AM on Monday, May 12, 2025. The detour will be done on Friday, May 16, 2025, by 5:00 AM. The detour is shown in yellow color on the attached PDF. The closed ramps are shown in red color.