Project Overview
This project is for concrete pavement repairs to the existing ramps and main Connector of the interchange. Work will also include structure guiderail approach modification, drainage upgrades, bridge barrier concrete patching, inlet repairs, guiderail upgrades, shoulder stabilization, permanent pavement markings, delineation, and post mounted signs. Maintenance and Protection of interchange traffic is also included.
Project construction activities started on Monday, July 24, 2023. Project completion date is October 17, 2025.
There are four phases to the project. Phase 1 included Ramp M , Ramp P, and Loop A which were completed during the 2023 construction season. Phases 2 through 4 are anticipated to be completed during the 2024 construction season. There will be some detouring of traffic during construction. 2025 Construction is anticipated to include Pavement Markings, Signage, and ancillary cleanup work.
The remaining phases are expected to be completed in 2024 and 2025.
Project Schedule
Anticipated T-028 Work Schedule:
Tuesday, April 2, 2024 through Friday, April 5, 2024:
Work will occur on Ramp R and Loop B. There is no detour. Work will occur during nightshift hours from approximately 7:00 PM to 5:30 AM. Traffic may be limited to a 12 feet minimum lane width on Ramp R and Loop B during work hours.
Tuesday, April 9, 2024 through Friday, April 12, 2024:
Work will occur on Ramp R and Loop B. Both will be closed with a detour. The detour will start around 5:00 AM on Monday, April 8, 2024. The detour will be done on Friday, April 12, 2024 by 5:00 AM. The detour is shown in green color on the attached PDF.
Monday, April 15, 2024 through Friday, April 19, 2024:
Work will occur on Ramp R and Loop B. Both will be closed with a detour. The detour will start around 5:00 AM on Monday, April 15, 2024. The detour will be done on Friday, April 19, 2024 by 5:00 AM. The detour is shown in green color on the attached PDF.