T-028 Cranberry Interchange

Traveling Construction T-028 Cranberry Interchange

Total Reconstruction Project

Project Overview

This project is for concrete pavement repairs to the existing ramps and main Connector of the interchange. Work will also include structure guiderail approach modification, drainage upgrades, bridge barrier concrete patching, inlet repairs, guiderail upgrades, shoulder stabilization, permanent pavement markings, delineation, and post mounted signs. Maintenance and Protection of interchange traffic is also included.

Project construction activities started on Monday, July 24, 2023. Project completion date is October 17, 2025.

There are four phases to the project.

Phase 1 included Ramp M, Ramp P, and Loop A which were completed during the 2023 construction season.

Phases 2 through 3 included Ramp J, Ramp JK, Ramp K, Ramp L, Ramp R, Loop B, and Structure S-23394 work were completed during the 2024 construction season.

Phase 4 will be completed in 2025 which includes the Eastbound Connector Road, Westbound Connector Road, Ramp A, Ramp B, Ramp N, for Concrete Pavement Patching, Pavement Markings, Signage, and ancillary cleanup work   There will be some detouring of traffic during construction. 

 

Project Maps

T-028 Project Ramp D Detour Drawing 7 of 8 Sheet 121 of 197

Click images above for high resolution versions.

Project Schedule

Construction will restart on the project on Monday, March 31, 2025. The contractor will be working night shift from 7:00 PM to 6:00 AM through Friday, April 4, 2025, to install measures for the Ramp D Detour. 

Monday, April 7, 2025 through May 9, 2025:  Work will occur on the Westbound Connector Road with a detour. The detour will start around 6:00 AM on Monday, April 7, 2025. The detour will be done on Friday, May 9, 2025 by 5:00 AM.  The detour is shown in yellow color on the map. 

The detour will NOT be in effect from a minimum 5:00 AM Friday mornings until 11:00 PM Sunday nights. At least one lane will be open from a minimum 5:00 AM Friday mornings until 11:00 PM Sunday nights.

T-028 Project Detour Map for Upcoming Phase 4B.1 Detour for PTC Website

Frequently Asked Questions

When did construction begin and how long will it take to complete?

How much will the project construction cost?

Will there be detours due to this project?

Will tolls have to be increased to pay for this project?

More Project Resources

Design & Construction Details

Find out about planned design & construction activities for this project.

Learn More

News & Public Involvement

Learn how we stay connected with the public about this project.

Stay Updated

Team & Contact Information

Learn about the team that we will work with to complete the work on this project.

Contact the Team