Anticipated T-028 Work Schedule:
Monday, April 1, 2024 through Friday, April 5, 2024:
Work will occur on Ramp R and Loop B. They are shown in red color on the attached PDF. There is no detour. Work will occur during nightshift hours from approximately 7:00 PM to 5:30 AM. Traffic may be limited to a 12 feet minimum lane width on Ramp R and Loop B during work hours.
Monday, April 8, 2024 through Friday, April 12, 2024:
Work will occur on Ramp R and Loop B. They are shown in red color on the attached PDF. Both will be closed with a detour. The detour will start around 5:00 AM on Monday, April 8, 2024. The detour will be done on Friday, April 12, 2024 by 5:00 AM. The detour is shown in green color on the attached PDF.
Monday, April 15, 2024 through Friday, April 19, 2024:
Work will occur on Ramp R and Loop B. They are shown in red color on the attached PDF. Both will be closed with a detour. The detour will start around 5:00 AM on Monday, April 15, 2024. The detour will be done on Friday, April 19, 2024 by 5:00 AM. The detour is shown in green color on the attached PDF.