Project Overview
This project section is 3.5 miles in length and includes widening the existing Turnpike mainline to accommodate six 12’ lanes with 12’ inside and outside shoulders. Also included in this section’s design are overhead and mainline structure (such as bridges and overpasses) replacements. The section begins approximately one mile east of the Allegheny Valley Interchange and traverses portions of the Borough of Oakmont and Plum Borough in Allegheny County. The project begins just east of where Hulton Road crosses over the Turnpike and ends just west of where Saltsburg Road crosses over the Turnpike.
Improvements to substandard mainline curves, bridge overhead vertical clearances and roadway widths will be included. All overhead bridges will be replaced and many of these replacements will be completed ahead of mainline widening.