Current Activities
- Mainline widening and reconstruction (Five main construction stages) started June 2022.
- Stage 3 of Construction – Traffic is on the newly constructed shoulders and right lanes (outside); the work zone is the left lanes and median (inside).

- Reconstructing the inside portions of two (2) Turnpike Mainline bridges:- B-346A – Turnpike Mainline over the Raystown Branch of the Juniata River.
- B-499A – Turnpike Mainline over New Baltimore Road (SR 3012 / SR 1015).
 
- Installing new right-of-way fence and access gates.
- Maintaining erosion and sedimentation control requirements.
Detours
- No current detours.
Project Map
 
    
 
         
                        
                 
                        
                 
                        
                 
                        
                 
                        
                 
                        
                 
                        
                 
                        
                 
                        
                 
                        
                 
                        
                 
                        
                 
                        
                 
                 
                 
                 
                 
                 
                 
                 
                 
                 
                 
                 
                