Stay in the know. Sign up for The Road Ahead to receive the latest PA Turnpike news.

Chat With Us

PA Turnpike Skip to main content
Restore English
Restore English
  •  E-ZPass Login
  •  Pay a Bill
  •  Toll Calculator
  •  Open Road Tolling
  •  Help Center
  •  About Us FAQs
  • E-ZPass
    • About E-ZPass
    • Purchase an E-ZPass
    • Register my E-ZPass
    • Personal Account
    • Commercial Account
    • Toll Calculator
    • All-Electronic Tolling
  • Toll By Plate
    • About Toll By Plate
    • Pay a Bill
    • Toll Calculator
    • PA Toll Pay App
    • All-Electronic Tolling
    • Open Road Tolling
    • Unpaid Tolls/Enforcement
  • Traveling
    • About Traveling
    • Toll Calculator
    • Active Travel Advisories
    • Service Plazas
    • Safety
    • 511PA Travel Information
    • Construction Projects
  • Commercial
    • About Commercial Travel
    • Commercial E-ZPass
    • Permits & Restrictions
    • Service Plazas
    • Toll Calculator
    • Hazardous Materials
  • Business Hub
    • About Working with Us
    • Vendor Portal
    • Vendor Guide
    • Bids & RFPs
    • Vendor Resources
    • Investor Relations
    • Existing Innovation Submission

Milepost A53-A57 Reconstruction - News

Milepost A53-A57 Northeast Extension News
  • Overview
  • News
  • Improvements
  • Engagement
  • Contact

Design Update

Stay up to date on the latest updates from our design activities.

Lower Macungie Bridge

Summer 2026 Update

  • East Texas Road Overhead Bridge
  • Final design plans available for review 
  • Advertised for construction with a scheduled bid opening on August 26, 2026
  • PPL has completed initial relocation of the aerial line
  • I-78 Overhead Bridge
  • Final design plan available for review
  • 90% complete
  • Coordinating with PPL on outages needed for the 500kv line over the bridge
  • Hamilton Boulevard Overhead Bridge
  • Final design plan available for review
  • Design is progressing toward 75% completion by Fall 2028
  • Coordinating with utilities: PPL, Verizon, AT&T and UGI
  • Coordinating National Pollutant Discharge Elimination System (NPDES) Permit application with Lehigh County Conservation District
  • Tilghman Street
  • Traffic on Tilghman Street and I-476 are operating under the permanent configuration.
  • Mill and overlay of Tilghman Street and I-476 were completed this spring along with Polyester Polymer Concrete (PPC) overlay of the bridge deck.
  • Project seeding and stormwater management facility work is expected to continue through summer into fall.

  • Commuters using Tilghman Street and I-476 may encounter daytime or nighttime lane closures. These closures will be sporadic for various operations required to complete the project.

  • Lower Macungie Road
  • Traffic on Lower Macungie Road, Millrace Road, Little Spur Road, and I-476 are operating under the permanent configuration.
  • Final paving of Little Spur Road and I-476 were completed this spring along with demolition of the existing bridge.
  • Project seeding and stormwater management facility work is expected to continue through the summer into fall.
  • Commuters using Lower Macungie Road and I-476 may encounter daytime or nighttime lane closures. These closures will be sporadic for various operations required to complete the project.

     

Spring 2026 Update

  • East Texas Road Overhead Bridge
  • Final design plans available for review 
  • 90% complete
  • PPL is relocating the aerial line
  • I-78 Overhead Bridge
  • Final design plan available for review
  • Design is progressing toward 90% completion by summer 2026
  • Draft National Pollutant Discharge Elimination System (NPDES) Permit application has been published in the PA Bulletin
  • Coordinating with PPL on outages needed for the 500kv line over the bridge
  • Continue coordination with PennDOT
  • Hamilton Boulevard Overhead Bridge
  • 60% design has been completed. Progressing towards 75%.
  • Coordinating with utilities: PPL, Verizon, AT&T and UGI
  • NPDES permit will be submitted in the second quarter of 2026
  • Other Updates
  • Stormwater management design and coordination with local municipalities continues
  • Overhead Bridges - The Tilghman Street Bridge (SR 1002) and Lower Macungie Road Bridge (SR 2012) are currently under construction. More details can be found on the Improvements Page in the Overhead Bridge section.
  • Mainline 1-476 - Preliminary engineering complete. Final design is currently on hold.
  •  

More Project Resources

Overview

Learn about this construction project.

Learn More

News

Learn the latest news about this project.

Stay Updated

Improvements

Learn about project improvements.

Learn More

Contact

Meet the team for this project.

Contact Team

  • About Us
    • Our Mission
    • Our Board of Commissioners
    • Commission Meeting Information
    • Our Executive Leadership
    • Design & Construction
    • PA Turnpike History
    • Investor Relations
    • Resource Library
    • Policies & Standards
    • Security & Fraud
    • About Us FAQs
  • News
    • Traffic Reports
    • The Road Ahead: Turnpike Newsletter
    • Stories from the Turnpike
    • Media Center
    • PA Turnpike Blogs
    • Right to Know Request
    • Law Enforcement Requests
    • Vehicle Registration Suspension Appeals
  • Responsibility Matters
    • Sustainability
    • Clean Water
    • Accountability
    • PA Mobility Partnership Reports
    • National Center for Missing and Exploited Children
    • Human Trafficking Awareness
  • Contract/PO Search
  • Careers
  • Contact Us
  • Site Map
  • Employee Login
  • Facebook
  • Twitter
  • Instagram
  • Linkedin
  • YouTube

©2026 The Pennsylvania Turnpike Commission