  • Delaware River Bridge I-beam Delaware River Bridge I-beam Delaware River Bridge I-beam

    Crews continue to work 24/7 on stabilizing towers that will be used to jack the bridge up to its previous alignment, determining the extent of the long term solution needed. Crews also continue to take borings from the bridge for analysis of the entire structure. Timeline remains the same, it will be another 6 weeks before crews know enough to issue next steps.
    Photo (click to download image #1 | click to download image #2) | click to download image #3)

  • Delaware River Bridge I-beam Delaware River Bridge I-beam

    On site crews continue to work around the clock at the Bridge work site erecting 80’ support towers that will eventually be used to support the jacking of the bridge into its original alignment. This work includes not only building the towers but digging and laying brand new foundations for each due to the ground conditions so close to the river. Relocation of some utilities was required and we are thankful for the support we received from all the local utility companies in doing this quickly and safely. The PA Turnpike Commission has been in contact with neighbors of the bridge who are impacted by the round the clock work to ensure they remain up to date on progress.
    Photo (click to download image #1 | click to download image #2)

  • Delaware River Bridge I-beam

    Section of the first of 8 80' temporary support towers nears completion at the Delaware River Bridge work site. These towers will be going up and will eventually allow engineers to realign the bridge and determine the long term solution.
    Photo (click to download)

  • Delaware River Bridge I-beam Delaware River Bridge I-beam Delaware River Bridge I-beam

    As crews continue critical repair work on the DRB, a snooper crane is used to inspect the other areas of the bridge for any defects or issues.
    Photo (click to download image #1 | click to download image #2 | click to download image #3)

  • Delaware River Bridge

    Crews are currently working below grade in eight locations to lay foundations for the temporary support towers which will further stabilize the compromised areas of the bridge. Cut-outs of the bridge have been sent to testing sites for analysis.
    Photo (click to download)

  • Delaware River Bridge I-beam Delaware River Bridge I-beam

    These photos show the splice plate installed over the weekend to stabilize the fractured I-beam. The arrows indicate the gap where the fracture occurred. That gap now looks bigger because steel samples were cut off the edges of the fracture and sent to a lab for analysis.
    Photo (click to download image #1 | click to download image #2)

  • Delaware River Bridge

    Delaware River Bridge, Bucks County, I-276
    Photo (click to download)

  • Delaware River Bridge

    Location of Fractured I-Beam
    Photo (click to download)

  • Delaware River Bridge

    The complete fracture occurred on a 14-inch truss member beneath the deck, or driving surface, of the Delaware River Turnpike Bridge. The affected truss member is located just below the westbound right lane of I-276 on the west shore.
    Photo (click to download)

  • Delaware River Bridge

    This photo shows the severed truss member looking up from below the Delaware River Turnpike Bridge. The fracture affects a section of the bridge on the PA side above Palmer Avenue. There are no residences or other structures beneath the bridge.
    Photo (click to download)