Construction Progress Photos

December 2024 - A side view of the new Hawk Falls Bridge during deck construction

December 2024 - The completed NB side of the new bridge over Hickory Run Road

December 2024 - Construction of the new NB approach lanes heading to the Hickory Run Bridge

November 2024 - A lift being used during construction of the new Hawk Falls Bridge

November 2024 - A topside view of the new Hawk Falls Bridge prior to installing the deck

November 2024 - Construction of the northbound side of the bridge over Hickory Run Road

October 2024 - Deck beam construction on the new Hawk Falls Bridge

October 2024 - A long view of the project area, looking south

October 2024 - The concrete riding surface in place on the NB side of the new Hickory Run Bridge

August 2024 - Construction of the approach to the new Hawk Falls Bridge

August 2024 - Workers begin to pave the NB side of the new Hickory Run Bridge

August 2024 - Deck construction begins on the Hawk Falls Bridge

August 2024 - Workers placing rebar prior to deck paving on the Hickory Run Bridge

July 2024 - Base paving for the Turnpike lane shift approaching the new Hawk Falls Bridge

July 2024 - Workers put the finishing touches on the arches for the Hawk Falls Bridge

July 2024 - A shot of the new arches beside the existing Hawk Falls Bridge

May 2024 - An underside view of workers connecting the arches for the Hawk Falls Bridge

May 2024 - Connecting the arches for the new Hawk Falls Bridge

May 2024 - Abutment construction for the new bridge over Hickory Run Road

March 2024 - Workers install the first span of "stringers" that will support the bridge's deck

March 2024 - Erecting the second set of temporary supports on the arch ribs

March 2024 - Workers install the first connection between the arch ribs on the new Hawk Falls Bridge

January 2024 - Construction of the new Hawk Falls Bridge, looking south

January 2024 - Abutment construction on the southern side of the Hawk Falls Bridge

January 2024 - A wide shot of the new Hawk Falls Bridge construction, looking north

December 2023 - Erection of the northern bridge arches

December 2023 - Construction of the new Hawk Falls Bridge, looking south

December 2023 - Construction of a retention pond

December 2023 - Construction of the new northern bridge approach roadway

November 2023 - Piles for the foundation of the north abutment of the new Hickory Run Bridge

November 2023 - Workers traverse a bridge arch close to its connection to the foundation

November 2023 - Hawk Falls Bridge arch erection, looking south

November 2023 - A large crane configuration for installation of the Hawk Falls Bridge arches

November 2023 - A long view of the project area with Hickory Run in the foreground, and Hawk Falls in the background

October 2023 - Abutment construction for the new Hickory Run Bridge

October 2023 - Close shot of the massive arch foundations for the new Hawk Falls Bridge

October 2023 - A close-up of the Hawk Falls Bridge arches

October 2023 - Partial segments of three bridge arches in place for the new Hawk Falls Bridge

September 2023 - A work crew erecting one of the Hawk Falls Bridge arches

September 2023 - Large cranes in place for the erection of the arch ribs that will support the new Hawk Falls Bridge

September 2023 - Excavation and construction of the Hawk Falls Bridge foundation

September 2023 - Temporary shoring in place for the construction of the new Hickory Run Bridge

September 2023 - One of the arch ribs that will support the new Hawk Falls Bridge awaiting placement

July 2023 - The long boom for the crane being assembled in the shoulder area

July 2023 - Counter-weights for the large crane

July 2023 - Assembling the track on the crawler of the large crane

July 2023 - Workers assemble the track for the crane to be used to erect the Hawk Falls Bridge arches

July 2023 - The long boom for the crane being assembled in the shoulder area

July 2023 - Construction of a decorative abutment wall for the new Hawk Falls Bridge nearing completion

July 2023 - Temporary roads in place to aid in the erection of the Hawk Falls Bridge arches this summer

July 2023 - Construction nearing completion on one of the project's drainage basins

July 2023 - Turnpike widening for construction of the new Hawk Falls Bridge

July 2023 - Excavation for shoring installation at the Hickory Run Road Bridge

May 2023 - Start of construction on the new bridge over Hickory Run Road

May 2023 - Decorative abutment wall for the new Hawk Falls Bridge

May 2023 - Backfilling an abutment wall for the new Hawk Falls Bridge

May 2023 - A long shot of the Hawk Falls Bridge work area being prepared for bridge arch erection this summer

May 2023 - Foundation construction for the new Hawk Falls Bridge

May 2023 - One of the project's new drainage basins

April 2023 - Abutment wall and foundations for the new Hawk Falls Bridge, looking north

April 2023 - Foundations for the new Hawk Falls Bridge, looking south

April 2023 - Recently poured concrete abutment for the new Hawk Falls Bridge

April 2023 - An abutment finished with decorative formliner

April 2023 - Pumping foundation concrete high above Mud Run Creek

February 2023 - Foundation construction for the new Hawk Falls Bridge

February 2023 - Foundation construction for the new Hawk Falls Bridge

February 2023 - Rebar in place for abutment construction

February 2023 - A long shot of the Hawk Falls Bridge project

November 2022 - Hawk Falls Bridge work area, looking north

November 2022 - Foundation pedestals at the northern abutment

November 2022 - Foundation construction for the new arch bridge

November 2022 - Northbound shoulder excavated for widening

November 2022 - Foundation construction for the new Hawk Falls Arch Bridge

November 2022 - Long shot of the new Hawk Falls Bridge construction, with existing bridge and crane in view

November 2022 - Drainage culvert construction for the new Hawk Falls Bridge

November 2022 - Excavation for a new Turnpike alignment, looking south

October 2022 - Excavation for new alignment looking south

October 2022 - Construction progresses on arch foundation for the Hawk Falls Bridge

October 2022 - Access road at Route 534 for Hawk Falls Bridge construction

October 2022 - Excavation for a drainage basin for the Hawk Falls Bridge

September 2022 - Installing support of excavation on the south side of the new Hawk Falls Bridge

September 2022 - Column footers on the north side of the Hawk Falls Bridge

September 2022 - In the background, foundation preparation for the north side of the new arch bridge

September 2022 - Starting the substructure for the new arch bridge

August 2022 - A closer look at foundation preparation on the north side

August 2022 - The existing Hawk Falls Bridge prior to demolition

August 2022 - Hawk Falls Bridge construction

July 2022 - Hickory Run Road (Rt. 534) Bridge drainage installation

July 2022 - New alignment excavation on the north side