Phase 1 began in 2018 with preliminary design and was completed in 2019. In 2020, there was a short pause in design activities due to the COVID-19 pandemic.
Phase 2 began in 2020 and final design activities are currently underway. A public meeting to present the design plans was held in 2022. The plans presented at the public meeting are available for review at this link.
As design concepts and/or schedule updates become available, they will be posted here.
![Updated Project Schedule_03_21_2024 Lafayette Street Interchange schedule shows final design complete in 2028 and construction beginning in 2028.](https://files.paturnpike.com/production/images/ptcconstructionsiteslibraries/lafayette-street/updated-project-schedule_03_21_202489746a05-a6c4-4049-acf2-a79f62fc1ddd.png?sfvrsn=2bf69f0e_1)