Fiscal Year 2007-2008 (in $000)
Roadway
 

1st Year Priority A (years 2-4) Priority B (years 5-7) Priority C (years 8-10) Total
Funding
Needed

Project Number - Title
2007 -
2008
2008 -
2009
2009 -
2010
2010 -
2011
2011 -
2012
2012 -
2013
2013 -
2014
2014 -
2015
2015 -
2016
2016 -
2017
T319.30RR001 - Slip Ramp Interchange, MP 319, Route 29 $4,350 $20,300 $20,000 $10,000 $0 $0 $0 $0 $0 $0 $54,650
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $1,450 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $300 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $200 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $2,000 $18,300 $18,500 $9,000 $0 $0 $0 $0 $0 $0  
  Inspect $400 $2,000 $1,500 $1,000 $0 $0 $0 $0 $0 $0  
T331.60RR001 - Lafayette Street Slip Ramps MP 331.60 $150 $150 $1,000 $4,000 $0 $10,000 $10,000 $20,000 $10,000 $20,000 $75,300
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $150 $150 $1,000 $4,000 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $9,000 $9,000 $19,000 $9,000 $19,000  
  Inspect $0 $0 $0 $0 $0 $1,000 $1,000 $1,000 $1,000 $1,000  
A087.00RR001 - Slip Ramp Interchange, MP A87.0, Route 903 $800 $1,500 $8,000 $3,800 $0 $0 $0 $0 $0 $0 $14,100
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $800 $500 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $200 $200 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $100 $100 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $650 $7,000 $3,000 $0 $0 $0 $0 $0 $0  
  Inspect $0 $50 $700 $800 $0 $0 $0 $0 $0 $0  
A030.13RR001 - Interchange Ramp Resurfacing, Lansdale Interchange, MP A30.13 and Quakertown Interchange, MP A43.77 $50 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $45 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $5 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T306.00RR006 - Pavement Repairs MP 306 - 318 (Construction) $10 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $10 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
A095.00RR001 - Bituminous Overlay M.P. A95 - A105 (Includes Concrete Median Barrier) $10 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $10 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
A049.00RR002 - Bituminous Overlay MP A49 -A59 (includes Concrete Median Barrier) $7,300 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,300
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $6,700 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $600 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T255.00RR001 - Bituminous Overlay M.P. 255 - 263 $50 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $50 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
V000.00RR042 - Philadelphia Area Interchange Paving Projects $2,300 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,300
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $2,100 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $200 $0 $0 $0 $0 $0 $0 $0 $0 $0  
A105.00RR001 - Bituminous Overlay M.P. A105 - A115 (Includes Concrete Median Barrier from MP A105 - A110 and milling and paving the Wyoming Valley Interchange Ramps) $6,700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,700
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $6,100 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $600 $0 $0 $0 $0 $0 $0 $0 $0 $0  
 
Total Number of Roadway Projects: 71 Totals: $273,450 $260,950 $241,750 $254,950 $252,880 $254,500 $252,200 $255,100 $274,100 $280,150 $2,600,030