Fiscal Year 2007-2008 (in $000)
Roadway
 

1st Year Priority A (years 2-4) Priority B (years 5-7) Priority C (years 8-10) Total
Funding
Needed

Project Number - Title
2007 -
2008
2008 -
2009
2009 -
2010
2010 -
2011
2011 -
2012
2012 -
2013
2013 -
2014
2014 -
2015
2015 -
2016
2016 -
2017
T199.00RR005 - Total Reconstruction: MP 199 - 202 (Constr. Phase) $0 $6,400 $9,800 $12,600 $6,500 $0 $0 $0 $0 $0 $35,300
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $5,750 $8,950 $11,500 $5,850 $0 $0 $0 $0 $0  
  Inspect $0 $650 $850 $1,100 $650 $0 $0 $0 $0 $0  
T215.00RR001 - Total Reconstruction: MP 215-220 (Constr. Phase) $0 $2,100 $5,600 $3,700 $0 $0 $0 $0 $0 $0 $11,400
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $1,900 $5,000 $3,250 $0 $0 $0 $0 $0 $0  
  Inspect $0 $200 $600 $450 $0 $0 $0 $0 $0 $0  
T220.00RR001 - Total Reconstruction: MP 220 - 227 (Constr. Phase) $0 $3,800 $7,200 $1,800 $0 $0 $0 $0 $0 $0 $12,800
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $3,450 $6,500 $1,550 $0 $0 $0 $0 $0 $0  
  Inspect $0 $350 $700 $250 $0 $0 $0 $0 $0 $0  
T031.20RR002 - Ultimate Warrendale (Constr. Phase) $0 $5,100 $9,400 $0 $0 $0 $0 $0 $0 $0 $14,500
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $4,600 $8,500 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $500 $900 $0 $0 $0 $0 $0 $0 $0  
T179.50RR001 - Total Reconstruction: MP 179.5-186 (Design Phase) $0 $0 $1,600 $2,400 $1,900 $0 $0 $0 $0 $0 $5,900
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $1,600 $2,200 $1,700 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $200 $200 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T312.00RR003 - Total Reconstruction - MP 312 - 319 (Design Phase) $0 $0 $0 $1,500 $2,400 $3,500 $3,500 $0 $0 $0 $10,900
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $1,500 $2,000 $2,500 $1,500 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $300 $200 $500 $0 $0 $0  
  Utility $0 $0 $0 $0 $100 $800 $1,500 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
V000.00RR048 - Total Reconstruction - Systemwide $0 $0 $0 $8,000 $60,400 $114,600 $136,000 $169,000 $200,000 $210,000 $898,000
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $8,000 $60,400 $114,600 $136,000 $169,000 $200,000 $210,000  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T138.00RR001 - Total Reconstruction MP 138-140 (Design Phase) $0 $0 $0 $0 $1,600 $3,000 $3,000 $0 $0 $0 $7,600
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $1,600 $2,700 $2,700 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $150 $150 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $150 $150 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T351.90RR001 - Bensalem Township Slip Ramps @ South Neshaminy Service Plaza MP 351.90 $2,400 $6,500 $0 $0 $0 $0 $0 $0 $0 $0 $8,900
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $300 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $1,800 $5,900 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $300 $600 $0 $0 $0 $0 $0 $0 $0 $0  
T080.00RR001 - Slip Ramp Interchange MP 80 $1,000 $0 $0 $5,000 $5,000 $10,000 $15,000 $20,000 $30,000 $10,000 $96,000
  Study $1,000 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $4,500 $5,000 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $300 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $200 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $9,000 $14,000 $19,000 $28,000 $9,000  
  Inspect $0 $0 $0 $0 $0 $1,000 $1,000 $1,000 $2,000 $1,000  
 
Total Number of Roadway Projects: 71 Totals: $273,450 $260,950 $241,750 $254,950 $252,880 $254,500 $252,200 $255,100 $274,100 $280,150 $2,600,030