Fiscal Year 2007-2008 (in $000)
Roadway
 

1st Year Priority A (years 2-4) Priority B (years 5-7) Priority C (years 8-10) Total
Funding
Needed

Project Number - Title
2007 -
2008
2008 -
2009
2009 -
2010
2010 -
2011
2011 -
2012
2012 -
2013
2013 -
2014
2014 -
2015
2015 -
2016
2016 -
2017
T040.00RR001 - Total Reconstruction MP. 40 - 48 (Design Phase) $2,500 $3,500 $3,000 $2,400 $0 $0 $0 $0 $0 $0 $11,400
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $2,500 $2,000 $2,000 $1,500 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $750 $500 $450 $0 $0 $0 $0 $0 $0  
  Utility $0 $750 $500 $450 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T319.00RR001 - Total Reconstruction: MP 319-326 (Design Phase) $2,500 $3,000 $2,000 $1,000 $0 $0 $0 $0 $0 $0 $8,500
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $2,000 $2,100 $1,000 $600 $0 $0 $0 $0 $0 $0  
  Right of Way $400 $500 $700 $200 $0 $0 $0 $0 $0 $0  
  Utility $100 $400 $300 $200 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T099.00RR002 - Total Reconstruction - MP 99 - 109 (Design Phase) $2,600 $4,000 $3,000 $1,000 $0 $0 $0 $0 $0 $0 $10,600
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $2,600 $2,500 $2,000 $500 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $1,000 $600 $400 $0 $0 $0 $0 $0 $0  
  Utility $0 $500 $400 $100 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T031.20RR001 - Total Reconstruction MP. 31.2 - 40 (Design Phase) $2,000 $500 $0 $0 $0 $0 $0 $0 $0 $0 $2,500
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $800 $200 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $1,000 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $200 $300 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T067.00RR001 - Total Reconstruction M.P. 67 - 75 (Design Phase) $2,000 $1,000 $0 $0 $0 $0 $0 $0 $0 $0 $3,000
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $1,000 $200 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $500 $300 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $500 $500 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
A020.00RR002 - Total Reconstruction: MP A20 - A30 $5,700 $18,800 $48,500 $61,200 $43,600 $47,300 $50,500 $12,000 $0 $0 $287,600
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $3,000 $2,400 $1,200 $1,400 $500 $0 $0 $0 $0 $0  
  Right of Way $500 $1,500 $1,300 $800 $0 $0 $0 $0 $0 $0  
  Utility $500 $900 $500 $300 $0 $0 $0 $0 $0 $0  
  Const $1,500 $12,500 $41,000 $53,000 $39,000 $42,500 $45,500 $10,900 $0 $0  
  Inspect $200 $1,500 $4,500 $5,700 $4,100 $4,800 $5,000 $1,100 $0 $0  
T199.00RR002 - Total Reconstruction M.P. 199 -214 (Design Phase) $2,500 $1,400 $1,100 $700 $0 $0 $0 $0 $0 $0 $5,700
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $1,800 $950 $800 $500 $0 $0 $0 $0 $0 $0  
  Right of Way $500 $250 $200 $150 $0 $0 $0 $0 $0 $0  
  Utility $200 $200 $100 $50 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T129.00RR001 - Total Reconstruction M.P. 128 - 134 (Design Phase) $2,000 $2,500 $1,000 $0 $0 $0 $0 $0 $0 $0 $5,500
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $2,000 $2,000 $1,000 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $300 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $200 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T242.00RR002 - Total Reconstruction: MP 242-245 (Design Phase) $2,000 $2,500 $0 $0 $0 $0 $0 $0 $0 $0 $4,500
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $1,800 $2,100 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $200 $200 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $200 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T149.50RR002 - Total Reconstruction M.P. 149.5 - 155.5 (Design Phase) $2,500 $2,500 $1,200 $0 $0 $0 $0 $0 $0 $0 $6,200
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $2,500 $2,000 $800 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $300 $300 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $200 $100 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
 
Total Number of Roadway Projects: 71 Totals: $273,450 $260,950 $241,750 $254,950 $252,880 $254,500 $252,200 $255,100 $274,100 $280,150 $2,600,030