Fiscal Year 2007-2008 (in $000)
FacilityProjects
 

1st Year Priority A (years 2-4) Priority B (years 5-7) Priority C (years 8-10) Total
Funding
Needed

Project Number - Title
2007 -
2008
2008 -
2009
2009 -
2010
2010 -
2011
2011 -
2012
2012 -
2013
2013 -
2014
2014 -
2015
2015 -
2016
2016 -
2017
T039.59FF001 - Recapitalization--Reconstruct Gibsonia Maintenance Section & District Facility $100 $10 $600 $7,700 $15,400 $0 $0 $0 $0 $0 $23,810
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $100 $10 $600 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $0 $7,000 $14,000 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $700 $1,400 $0 $0 $0 $0 $0  
T243.85FF005 - Recapitalization--New Cumberland Tower Replacement $30 $0 $0 $0 $0 $0 $0 $0 $0 $0 $30
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $25 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $5 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
V000.00FF074 - Recapitalization--Communications System Tower Replacement Various Locations $320 $0 $0 $0 $0 $0 $0 $0 $0 $0 $320
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $25 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $295 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T075.39FF002 - Recapitalization--Renovations at New Stanton Interchange $10 $200 $2,500 $0 $0 $0 $0 $0 $0 $0 $2,710
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $10 $200 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $0 $0 $2,300 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $200 $0 $0 $0 $0 $0 $0 $0  
V000.00FF075 - Recapitalization--Toll Plaza Facility Renovations Various Locations $300 $340 $500 $600 $0 $0 $0 $0 $0 $0 $1,740
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $100 $40 $50 $100 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $200 $300 $450 $500 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T063.22FF002 - Recapitalization--Replace Harrison City Maintenance Salt Storage Facility $260 $0 $0 $0 $0 $0 $0 $0 $0 $0 $260
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $260 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T154.42FF003 - New Initiative--Construct Centralized Fare Collection Warehouse at Everett $350 $1,500 $0 $0 $0 $0 $0 $0 $0 $0 $1,850
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $150 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $200 $1,500 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
T333.59FF001 - New Initiative--Relocate Plymouth Meeting Maintenance Section and District 4 Maintenance Operations $3,050 $13,000 $11,000 $0 $0 $0 $0 $0 $0 $0 $27,050
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $400 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $2,450 $12,000 $10,000 $0 $0 $0 $0 $0 $0 $0  
  Inspect $200 $1,000 $1,000 $0 $0 $0 $0 $0 $0 $0  
T330.14FF002 - New Initiative--Eastern Regional Office Second Floor Development $2,100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,100
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $2,000 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $100 $0 $0 $0 $0 $0 $0 $0 $0 $0  
A043.77FF002 - New Initiative -- Quakertown Maintenance, New Salt Storage Facility $740 $0 $0 $0 $0 $0 $0 $0 $0 $0 $740
  Study $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Design $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Right of Way $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Utility $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Const $740 $0 $0 $0 $0 $0 $0 $0 $0 $0  
  Inspect $0 $0 $0 $0 $0 $0 $0 $0 $0 $0  
 
Total Number of FacilityProjects Projects: 61 Totals: $30,520 $38,700 $41,200 $33,700 $34,700 $34,700 $33,100 $38,000 $38,600 $39,000 $362,220