Construction Activities - May 21-26 - Post 1 of 2

May 17, 2012

I-476 MAINLINE CONSTRUCTION – May 21-26, 2012

Due to the Memorial Day holiday, no construction-related lane closures will occur on I-476 between 3 p.m. Thursday (5/24) and 6 a.m. Wednesday (5/30) except in emergencies

Jocelyn Road, Hickory Road – DAY
Plymouth Township
• Installing retaining walls Monday (5/21) through Friday (5/25) from 7 a.m. – 6:30 p.m.

Walton Road, Apollo Road, Township Line Road – DAY
Plymouth Township
• Excavating mainline and installing retaining walls Monday (5/21) through Friday (5/25) from 7 a.m. – 6:30 p.m.

Walton Rd., Fountain Rd., Allandale Rd., Colton Dr., Loretta Ln., Timberfare Cr., Jolly Rd. – DAY
Plymouth Township
• Excavating mainline and installing retaining walls Monday (5/21) through Friday (5/25) from 7 a.m. – 6:30 p.m.

Union Meeting Road, Jolly Road – DAY
Plymouth Township
• Installing drainage and milling to subgrade Monday (5/21) through Friday (5/25) from 7 a.m. – 6:30 p.m.

Sheffield Drive, Larchwood Drive, Old Arch Road – DAY
Whitpain Township
• Installing retaining walls Monday (5/21) through Friday (5/25) from 7 a.m. – 6:30 p.m.

Jolly Road, Meadow Drive, Mermaid Lake – DAY
Whitpain Township
• Installing retaining walls Monday (5/21) through Friday (5/25) from 7 a.m. – 6:30 p.m.

Wentz Road, Horseshoe Drive, Lucy Drive, Michaels Lane, DeKalb Pike, Cherry Road – DAY
Whitpain Township
• Excavating mainline Monday (5/21) through Friday (5/25) from 7 a.m. – 6:30 p.m.

Jolly Road, Meadow Drive, Wick Lane, DeKalb Pike – DAY
Whitpain Township
• Excavating mainline Monday (5/21) through Friday (5/25) from 7 a.m. – 6:30 p.m.

North Wales Road, Crestline Drive, Deep Meadow Drive, Oak Terrace, Shady Lane – DAY
Worcester Township
• Excavating to subgrade and installing drainage Monday (5/21) through Friday (5/25) from 7 a.m. – 6:30 p.m.

Skippack Pike, Bethel Road, Berks Road – DAY
Worcester Township
• Installing drainage Monday (5/21) and Tuesday (5/22) from 7 a.m. – 6:30 p.m.

Work continued in next post

ALL WORK IS DEPENDENT ON THE WEATHER AND THE CONTRACTOR’S ACCESSIBILITY AND/OR PRODUCTIVITY AND IS SUBJECT TO CHANGE