Roadway & Bridge Reconstruction MP 31.04 to 37.82: Current Construction |
| Motorists
traveling the Pennsylvania Turnpike in the vicinity of this
reconstruction are advised that all lanes are currently open to traffic. |
SEPTEMBER 2010
|
The
contractor is continuing to work Monday through Friday on two (2) shifts
(7:00 am to 5:30 pm & 7:00 pm to 3:00 am)
throughout the project.
Night
shift single lane closures are scheduled Monday through Friday, and
will occur sometime between 7:00 pm and 7:00 am. Current
construction activities include clearing & grubbing, erosion &
sedimentation controls, excavation, embankment, drainage/pipe
installation, paving and reconstruction of structures and culverts.
Project operations are ongoing both eastbound and westbound at
various locations between mileposts 30.5 and 37.8.
|
|
|
Current
construction activity information is periodically updated. Check back
often for the latest news on activity that may affect your journey.
|
|
|