Construction Activities - July 30 - August 4 - Post 1 of 2

July 26, 2012

I-476 MAINLINE CONSTRUCTION – July 30 - August 4, 2012
Daytime (D) Hours: 7 a.m. – 6:30 p.m.
Night (N) Hours: 6:30 p.m. – 5 a.m. 
Day/Night (D/N): 24 hours a day

Roadway and Earthwork Monday (7/30) through Saturday (8/4)
(excavating, installing drainage, placing and fine-grading subbase, placing and grading hardrock, paving, installing erosion & sediment controls, installing noise wall posts)

Plymouth Township
Walton Rd., Apollo Rd., Township Line Rd. – D

Walton Rd., Fountain Rd., Allandale Rd., Colton Dr., Loretta Ln., Timberfare Cr., Jolly Rd. – D

Whitpain Township
Union Meeting Rd., Jolly Rd. – D

Wentz Rd., Horseshoe Dr., Lucy Dr., Michaels Ln., DeKalb Pk., Cherry Rd. – D/N

Jolly Rd., Meadow Dr., Wick Ln., DeKalb Pk. – D/N

Worcester Township
North Wales Rd., Crestline Dr., Deep Meadow Dr., Oak Ter., Shady Ln. – D

Structures Monday (7/30) through Friday (8/3)
(constructing abutments and wingwalls, backfilling, excavating, drilling nails, installing mesh & shotcrete, installing overhangs and deck rebar)

Plymouth Township
Hickory Rd. Mainline Bridge – D
Township Line Rd. Mainline Bridge – D

Whitpain Township
Jolly Rd. Mainline Bridge – D
Wentz Rd. Mainline Bridge – D/N

Worcester Township
North Wales Rd. Mainline Bridge – D
Skippack Pk. Mainline Bridge – D

ALL WORK IS DEPENDENT ON THE WEATHER AND THE CONTRACTOR’S ACCESSIBILITY AND/OR PRODUCTIVITY AND IS SUBJECT TO CHANGE