January
- March
Complete prep. work and switch traffic patterns on
mainline Eastbound and Westbound
April
- June
Stage 1 Roadway Reconstruction
Total reconstruction of Westbound shoulder, travel
lane and portion of passing lane
Total reconstruction of westbound ramps to and from
Butler Valley toll plaza
June
- August
Stage 2 Roadway Reconstruction
Total reconstruction of remaining portion of WB passing
lane, median, and portion of EB passing lane
Mill and pave ramps from Bulter Valley Interchange
to and from SR 008.
August
- November
Stage 3 Roadway Reconstruction
Total reconstruction of remaining portion of Eastbound
passing lane, Eastbound travel lane and shoulder
Total reconstruction of eastbound ramps to and from
Butler Valley toll plaza
April
- November
Bridge Rehabilitation
Westbound-416 (Turnpike over Willow Run) apply anti-graffiti
coating to parapets
Westbound-417 (SR 4067 over Turnpike) apply anti-graffiti
coating to concrete substructure
Westbound-420 (SR008 over Turnpike) concrete pedestal
and spall repair, paint steel superstructure, apply
anti-graffiti coating to concrete substructure and
parapets
Westbound-420A (Ramp AB over Turnpike) reconstruct
concrete pedestals, parapets and cheek walls, concrete
spall repairs, reset bearings, paint steel superstructure,
apply anti-graffiti coating to concrete substructure
and parapets
Westbound-420C (retaining wall Ramp AB) concrete spall
repair, apply anti-graffiti coating
Miscellaneous:
Repair/replace right-of-way fence, traffic signs and
highway lighting
October
- November
Stage 4
Install permanent concrete median barrier and perform
final median work
|